Schedule risk review is an AI agent skill from the GitHub repository mariourquia/cre-skills-plugin. Reviews current schedule against baseline, identifies critical-path risks, recomputes completion and stabilization probability, and routes a rebaseline proposal when warranted. Integrates with `workflows/cost_to_complete_review` and `workflows/draw_package_review` for financial consequences.

How to use this skill

Skill file

Schedule Risk Review

Workflow purpose

Keep the project schedule honest. Measure slip, name the cause, quantify the cost and lease-up downstream impact, and route any rebaseline.

Trigger conditions

Inputs (required / optional)

| Input | Type | Required | Notes |

|---|---|---|---|

| Current schedule | record | required | |

| Baseline schedule | record | required | |

| Milestone record | table | required | baseline vs. current forecast |

| Critical-path disruption log | log | optional | |

| Duration assumption overlay | csv | required | |

| Lease-up plan (if applicable) | record | optional | |

Outputs

| Output | Type | Shape |

|---|---|---|

| Schedule delta view | kpi_review | schedule_variance_days, milestone_slippage_rate |

| Critical-path memo | memo | cause, cost impact, lease-up impact |

| Rebaseline proposal | memo | with approval path |

| Lease-up delivery scenario | kpi_review | lease_up_pace_post_delivery / stabilization_pace_vs_plan |

Required context

Asset_class, segment, form_factor, market, project.

Process

  1. Compute schedule delta. schedule_variance_days and milestone_slippage_rate.
  2. Classify cause. Trade delay, material lead time, permit, weather, design, labor, owner decision.
  3. Critical-path analysis. Determine whether slip is on critical path.
  4. Cost consequence. Link to workflows/cost_to_complete_review (escalation, labor, carry cost).
  5. Lease-up consequence (if applicable). Link to lease_up_pace_post_delivery and stabilization_pace_vs_plan.
  6. Rebaseline recommendation. If slip exceeds overlay threshold, recommend rebaseline; opens approval_request per overlay.
  7. Confidence banner. References surfaced.

Metrics used

schedule_variance_days, milestone_slippage_rate, punchlist_closeout_rate, lease_up_pace_post_delivery, stabilization_pace_vs_plan.

Reference files used

Escalation points

Required approvals

Failure modes

  1. Slip view without critical-path analysis. Fix: step is mandatory.
  2. Missing cost consequence link. Fix: invokes CTC review.
  3. Silent rebaseline. Fix: rebaseline is an approval.
  4. Lease-up impact ignored. Fix: lease-up scenario mandatory when applicable.

Edge cases

Example invocations

  1. "Run schedule risk review for Willow Creek."
  2. "What's the critical-path slip on the South End renovation?"
  3. "Lease-up impact if framing slips 30 days on Riverbend."

Example outputs

Output — Schedule risk (abridged, Willow Creek April)

Slip. schedule_variance_days within overlay band; milestone_slippage_rate within band.

Cause. One trade's material lead time on one milestone; non-critical path.

Cost. Minor carrying cost; CTC review to confirm.

Lease-up. No material change to expected TCO.

Rebaseline. Not recommended.

Confidence banner. construction_duration_assumptions__southeast@2026-03-31 (starter).