Draw package review is an AI agent skill from the GitHub repository mariourquia/cre-skills-plugin. Reviews a draw package end to end before lender submission. Validates construction cost to date, reconciles to the lender requisition, confirms lien waivers by vendor and period, verifies insurance endorsements, checks compliance attestations, and evaluates cost-to-complete. Splits construction mana

How to use this skill

Skill file

Draw Package Review

Workflow purpose

Every construction draw is load-bearing for the project's financial trajectory and for the lender's view of risk. This workflow takes the assembled draw package, runs it through the construction manager's review and the asset manager's review in sequence, verifies every attachment (lien waivers, insurance endorsements, compliance attestations), recomputes cost-to-complete, and opens the two gated approvals: the internal approval that the draw is ready to submit (row 12), and the final lender submission (row 14).

This pack is flagship-depth. It is where construction discipline and ownership discipline meet. It is also where the most common silent-failure modes live: stale lien waivers, missing insurance endorsements, change orders not yet reflected in the requisition, and cost-to-complete drift. Each of those is a hard check in this workflow.

Trigger conditions

Inputs (required / optional)

| Input | Type | Required | Notes |

|---|---|---|---|

| Draw package | bundle | required | requisition, G702/G703 or lender format, attachments |

| Budget and contract register | record | required | original + all COs |

| Cost-to-date report | report | required | GC pencil + owner's rep recut |

| Change orders | table | required | approved + pending + rejected |

| Lien waivers | docs | required | conditional current period, final prior period |

| Insurance certificates and endorsements | docs | required | builders risk, GL, umbrella, auto, workers comp |

| Compliance attestations | docs | required | per loan |

| Schedule update | record | required | current forecast |

| Lender draw requirements overlay | yaml | required | per loan |

| Prior draw record | record | required | for continuity |

Outputs

| Output | Type | Shape |

|---|---|---|

| Construction manager review checklist | checklist | per attachment, per line item |

| Asset manager review memo | memo | financial, schedule, risk |

| Cost-to-complete refresh | kpi_review | per trade, per project |

| Attachment gap list | checklist | missing lien waivers, insurance, attestations |

| Internal approval request | request | row 12 (submission readiness) |

| Final lender submission request | request | row 14 |

| Draw cycle tracking | record | draw_cycle_time update |

Required context

Asset_class, segment, form_factor, market, project, loan (for requirements overlay).

Process

Step 1. Stages of the draw.

A draw package, in this workflow, has five layered stages that are verified in order. The workflow refuses to advance a stage with an open gap.

Stage 1. Construction cost to date.

Stage 2. Lender requisition.

Stage 3. Lien waivers.

Stage 4. Insurance and bonding.

Stage 5. Compliance attestations.

Step 2. Construction manager's review responsibilities.

The construction manager's review covers the physical and contractual integrity of the draw:

The construction manager marks the draw "CM-reviewed" when Stages 1-5 pass. Any unresolved gap routes to the GC or the owner's rep for fix before advancement.

Step 3. Asset manager's review responsibilities.

The asset manager's review covers the financial and risk posture of the draw:

The asset manager marks the draw "AM-reviewed" when the financial and risk posture is acceptable. The asset manager opens approval_request row 12 for submission readiness.

Step 4. Internal approval (row 12).

Row 12 is the internal approval that the draw package is ready to submit to the lender. Minimum approvers: construction_manager + asset_manager. The approval record carries the draw number, the period, the requisition total, the cost-to-complete at this period, contingency remaining, and a brief narrative.

Step 5. Lender final submission (row 14).

A draw is a lender-facing submission marked final. Row 14 governs any lender-facing final submission; an approved row 14 record is required before the package leaves the organization. Minimum approvers: asset_manager + finance/reporting lead. The workflow holds the package (does not transmit) until approval returns approved.

Step 6. Submission and tracking.

On approved row 14, the package is released. The workflow records submission timestamp; cycle-time clock starts; status moves to "submitted-to-lender".

Step 7. Funding close-out.

On lender funding, the workflow updates draw_cycle_time, updates disbursement records, and flags any lender callbacks or questions for the construction manager.

Step 8. Confidence banner.

Surface: lender requirements overlay as_of_date and status; estimator baseline as_of_date; insurance certificate expiration dates; lien waiver period coverage; contingency assumption as_of_date. Any sample-tagged reference is explicit.

Decision points and branches

Metrics used

cost_to_complete, contingency_remaining, contingency_burn_rate, change_orders_pct_of_contract, schedule_variance_days, milestone_slippage_rate, draw_cycle_time, capex_spend_vs_plan (program-level feeder).

Reference files used

Escalation points

Required approvals

Failure modes

  1. Including unapproved COs in requisition. Fix: any pending CO is excluded; approved COs only.
  2. Stale lien waiver (prior period final waiver missing). Fix: hard gate; submission held.
  3. Insurance endorsement misaddressed to wrong insured. Fix: overlay-driven named-insured check.
  4. Compliance attestation missing. Fix: hard gate; per loan overlay.
  5. Cost-to-complete silent drift. Fix: recompute every draw; flag vs. trailing 3 and 6.
  6. Contingency over-burn hidden by reallocation. Fix: contingency burn-rate metric explicit; reallocation memo required.
  7. Submission without row 14 approval. Fix: transmission gated.
  8. Retainage misapplied. Fix: overlay retainage policy is the reference.
  9. Sample overlay treated as loan-doc. Fix: lender_draw_requirements__{loan}.yaml must be loan-specific; sample tag surfaced at runtime.

Edge cases

Example invocations

  1. "Review the April draw for the Willow Creek construction project. It's due to the lender on the 25th."
  2. "Run the CM and AM reviews on draw #7 for the Riverbend development."
  3. "Cost-to-complete trending off for the South End renovation. Pull the most recent draw and pressure-test."

Example outputs

Output — Draw review (abridged, April draw, Willow Creek)

Stage 1 — Cost to date. Reconciled to contract register. Three COs approved and included; one pending CO excluded. GC pencil aligned with owner's rep recut within overlay tolerance.

Stage 2 — Requisition. Lender format matches loan overlay. Soft-cost categories conform to loan-doc definitions. No budget reallocation this period.

Stage 3 — Lien waivers. Prior-period final waivers present for every vendor paid. Current-period conditional waivers present and valid. State-specific language verified per jurisdiction overlay.

Stage 4 — Insurance. Builders risk in force through period; named-insured clause matches. GC GL, umbrella, auto, workers comp current. Two subcontractors above overlay threshold: COI on file, endorsement current.

Stage 5 — Compliance attestations. All required attestations present per loan overlay.

CM review. "CM-reviewed" status set.

AM review.

Approvals. approval_request row 12 opened and approved. approval_request row 14 opened; pending lender final submission approval.

Submission. Held pending row 14 approval. On approval, package releases and cycle-time clock starts.

Confidence banner. lender_draw_requirements__loan_willow_creek@2026-01-15, status=sample (loan-doc overlay pending confirmation). capex_line_items__scope@2026-03-31, status=starter. labor_rates__charlotte@2026-03-31, status=sample. contingency_assumptions@2026-03-31, status=starter.

Output — Cost-to-complete pressure test (abridged, South End renovation)

Trigger. Cost-to-complete trending above plan beyond overlay threshold on recent draws.

Findings. Material-cost drift on two line items; labor hours above estimator baseline on a third. workflows/cost_to_complete_review invoked for deeper analysis.

Draw impact this period. Current draw does not yet require contingency drawdown; however, trajectory implies contingency pull within 2-3 draws.

Recommendation. AM to convene CM and estimator; owner-side remediation plan needed before next draw. Draw may still submit with notation.

Confidence banner. As above.