Development pipeline tracking

From mariourquia/cre-skills-plugin · View interactive version

Development pipeline tracking is an AI agent skill from the GitHub repository mariourquia/cre-skills-plugin. Weekly roll-up of the active development pipeline. Aggregates sites under contract, in entitlement, in design, in permitting, and in construction (by phase); tracks TCO/delivery target dates, baseline-vs-current schedule slip, baseline-vs-current cost slip, change-order trend, draw schedule status,

How to use this skill

Skill file

Development Pipeline Tracking

Workflow purpose

Give development_lead, construction_lead, and asset_mgmt_director a single weekly

view of the active development pipeline — from deal close through delivery — so that

slip on any project surfaces against the portfolio baseline in the same week it

happens.

This pack is a tracker. It never authorizes a rebaseline, a scope change, a CO, or a

contingency pull. It flags, it aggregates, and it routes into the owning workflow.

The workflow is intentionally read-heavy across three source systems (Dealpath for

deal-side posture, Procore for construction state and commitments, Intacct for

posted capex spend) and depends on the cross-system reconciliation posture declared

in _core/stack_wave4/source_of_truth_matrix.md.

Trigger conditions

review", "critical-path slip this week", "what's slipping in construction",

"development dashboard".

slipped vs. baseline; Dealpath closed-deal handoff lag exceeds overlay tolerance

(dp_handoff_dev_lag); commitment overdrawn check fires

(pc_recon_commitment_overdrawn); capex spend-to-plan breaches overlay band;

lease-up readiness deadline approaching for any project.

org convention).

Inputs (required / optional)

| Input | Type | Required | Notes |

|---|---|---|---|

| Dealpath deal register | table | required | all deals at stage in {sourced, under_contract, ic_approved, closing, funded} |

| Dealpath deal-milestone log | table | required | per-deal milestone state |

| Procore project roster | table | required | all active construction_projects |

| Procore schedule milestone log | table | required | baseline + current_forecast per milestone |

| Procore commitment register | table | required | open commitments, paid_to_date, retention |

| Procore change-order register | table | required | approved + pending |

| Procore draw-request log | table | required | submitted, approved, funded dates |

| Intacct actuals feed (capex) | table | required | posted spend by capex_project dimension |

| Intacct invoice register | table | required | AP posting status for commitments |

| Dev_project_crosswalk | yaml | required | dealpath deal <-> procore project <-> intacct project |

| Capex_project_crosswalk | yaml | required | procore project <-> intacct project |

| Schedule-milestone baseline | record | required | preserved per project |

| Construction duration assumptions | csv | required | region-scoped |

| Tolerance-band schema | yaml | required | reconciliation_tolerance_band.yaml |

| Weather / jobsite log | log | optional | for weather-delay narrative |

| Contractor performance scorecard | record | optional | cross-project GC / major sub |

Outputs

| Output | Type | Shape |

|---|---|---|

| Pipeline dashboard by stage | dashboard | sites_under_contract, in_entitlement, in_design, in_permitting, in_construction (by phase) |

| Schedule posture | kpi_review | schedule_variance_days, milestone_slippage_rate, critical_path_slip_days (proposed) per project |

| Cost posture | kpi_review | cost_to_complete, contingency_remaining, contingency_burn_rate, change_orders_pct_of_contract, trade_buyout_variance |

| Draw posture | kpi_review | draw_cycle_time, draw_burn_rate_vs_plan (proposed), open draws, funded YTD |

| Commitment exposure | kpi_review | commitment_exposure_forward_dollars (proposed), commitments-overdrawn list |

| Delivery outlook | kpi_review | TCO/delivery target per project, slip vs. baseline, cco_to_first_lease_days (proposed) where applicable |

| Lease-up readiness | kpi_review | projects within 180 days of delivery; gating items |

| Financing draw status | kpi_review | per-project draw schedule state vs. lender calendar |

| Regional / deal-lead rollup | dashboard | by region; by deal_lead |

| Reconciliation posture | memo | dp_handoff_dev_lag, pc_recon_commitment_overdrawn, pc_recon_commitment_vs_posted_spend findings |

| Narrative memo | memo | 3-5 paragraphs, cited metrics, top-3 watch items |

| Confidence banner | banner | reference as_of + status |

Required context

Asset_class, segment, region (one or many), deal_lead (optional filter). Project

grain rolls up to region + deal_lead. Axis project_id is optional (omit to get a

pipeline-wide view; supply to get a single-project drill-down); when omitted, the

workflow aggregates across all active development projects in the org overlay's

scope.

Process

Step 1. Pipeline stage snapshot

Assemble stage buckets from Dealpath and Procore:

development_project.entitlements_status = in_process).

foundation, framing, mep_rough, drywall, finishes, punchlist, closeout}).

Source-of-truth: per source_of_truth_matrix.md, Dealpath is primary for deal

and development_project (pre-handoff); Procore is primary for

construction_project once the project executes. Surface any site stuck in

transition (e.g., Dealpath says funded but Procore project not yet created).

Step 2. Schedule posture

For each active construction project:

critical_path_flag = true milestones.

reconciliation_tolerance_band.yaml).

time, labor, owner decision, design. Hand off to workflows/schedule_risk_review

for any project whose slip crosses the overlay rebaseline trigger.

Step 3. Cost posture

For each active construction project:

output. Do not recompute here.

commitment register and Intacct posted spend.

breaching the overlay band without a change-order trail.

cost — route to workflows/cost_to_complete_review.

Step 4. Commitment exposure

Use Procore commitment register (per source_of_truth_matrix.md, Procore is

primary for commitment; Intacct reconciles posted spend):

all active projects, grouped by region and by trade.

revised_contract_total + overdrawn_tolerance_band`. Cite

pc_recon_commitment_overdrawn on any breach; route to the runbook at

reference/connectors/adapters/procore_construction/runbooks/procore_common_issues.md::commitment_overdrawn.

reconciliation_tolerance_band.yaml::co_posting_lag_band (Intacct has not

posted within the lag window) — these are audit entries, not blockers.

Step 5. Change-order trend

For each project:

unforeseen) per ChangeOrder.category. Surface any shift in mix (e.g., rising

share of design_error COs triggers a design-team review conversation).

Step 6. Draw posture

For each project with a construction loan:

where the lender's draw plan is available.

workflows/draw_package_review for next submission cycle context.

Step 7. Contractor performance flag

Pull cross-project contractor performance scorecard (optional input). For each

major GC / sub:

to this contractor.

across multiple projects) — if two+ projects show signals, flag as

subcontractor_distress and route to the construction_manager queue.

Step 8. Delivery outlook & lease-up readiness

For projects in the last 180 days before expected TCO / certificate of occupancy:

model-unit readiness, staffing plan in place.

actual gap; for pre-delivery projects, the planned gap per lease-up plan.

window.

Step 9. Financing draw status

For each project:

dates.

waiver gap) — route to workflows/draw_package_review.

Step 10. Reconciliation posture across source systems

Cite and surface the following cross-system reconciliation findings from the

adapter contracts:

dev_handoff_lag_threshold_days). Cite the rule id and the runbook at

reference/connectors/adapters/dealpath_deal_pipeline/runbooks/dealpath_common_issues.md::dev_handoff.

Any blocker puts the affected project into low_confidence on the dashboard and

the reconciliation memo lists the exception with runbook pointer.

Step 11. Regional and deal-lead rollup

Group the project-level views by:

slip-days average per deal_lead.

Step 12. Top-3 watch items

Narrative synthesis: name the three most consequential pipeline watch items this

week. Each watch item cites: the project, the metric slug, the tolerance band

reference, the owning workflow, and the proposed next action.

Step 13. Confidence banner

Every reference surfaced with as_of_date and status. Any sample-tagged

reference is explicit. Cross-system reconciliation findings cited by rule id.

Decision points and branches

workflows/schedule_risk_review. Do not rebaseline here.

workflows/cost_to_complete_review.

approve any new draw on that project until resolved.

dealpath runbook pointer.

workflows/lease_up_first_period.

workflows/draw_package_review.

Metrics used

See frontmatter. Canonical metrics are inherited from

workflows/schedule_risk_review, workflows/cost_to_complete_review, and

workflows/draw_package_review. The proposed metrics

(critical_path_slip_days, draw_burn_rate_vs_plan, cco_to_first_lease_days,

handoff_lag_dealpath_to_procore, commitment_exposure_forward_dollars) are

aggregations required by the pipeline-tracking use case; formal promotion into

_core/metrics.md happens in a follow-up canonical change-control cycle.

Reference files used

Escalation points

workflows/schedule_risk_review.

draws held until resolved.

Required approvals

None for the tracker itself (informational / recommendation severity).

Downstream owning workflows carry their own approval gates (rebaseline -> row

per overlay; capex reallocation -> row per overlay; draw final submission ->

row 14; CO approval -> row 10 / 11).

Failure modes

  1. Treating Dealpath deal stage as project state. Fix: stage semantics are in

Dealpath adapter's normalized_contract.yaml; project state is in Procore.

Surface both where relevant; never collapse.

  1. Computing critical-path slip without the critical_path_flag. Fix:

critical_path_slip_days (proposed) is restricted to milestones with

critical_path_flag = true. Document the filter in output.

  1. Commitment overdrawn silently accepted because Procore reconciliation view

not surfaced. Fix: pc_recon_commitment_overdrawn is an explicit check every

run; any hit appears as a blocker on the dashboard.

  1. Dealpath closed deal without Procore project not flagged. Fix:

dp_handoff_dev_lag is cited every run; rule id and threshold live in the

dealpath adapter dq_rules.

  1. Inheriting CTC values from a stale cost-to-complete review. Fix: each

project's CTC carries its own as_of_date; stale CTCs are annotated.

  1. Regional / deal-lead rollup drawn without the axis filter. Fix: rollup views

are explicit filters; not the default view.

  1. Draw burn-rate computed without the lender's draw plan. Fix:

draw_burn_rate_vs_plan is skipped for projects without a lender plan and

annotated as "no_lender_plan" in the dashboard.

  1. Sample overlay treated as authoritative. Fix: confidence banner surfaces

sample-tag explicitly.

Edge cases

construction_duration_assumptions__{region}.csv). Variance beyond overlay is

the flag. Regional rollup groups weather-attributable slip separately from

other slip so the narrative does not conflate.

subcontractor_distress; trigger legal_and_risk review. A single affected

project routes through workflows/schedule_risk_review per normal; the

pipeline tracker only flags the cross-project pattern.

workflows/schedule_risk_review changes the project's current baseline. This

tracker preserves prior baseline in the baseline_reset_history section of

the narrative and clearly notes the rebaseline date; schedule_variance_days

uses the current approved baseline for comparison but the memo surfaces both

to prevent silent drift across weekly runs.

funding shows in sites_under_contract` with a sub-tag. Do not yet create a

Procore project expectation; the handoff clock starts at funding.

source-of-truth matrix. Cost posture for that project is unreconciled;

dashboard annotates no_intacct_mapping.

workflows/change_order_review.

cco_to_first_lease_days (proposed) calculation starts from CCO.

Example invocations

  1. "Run the weekly development pipeline tracker. Flag critical-path slip beyond tolerance."
  2. "Pipeline dashboard by region for the Southeast portfolio."
  3. "What's the deal-lead exposure for Alex this week? Include cost and schedule posture on each project."
  4. "Check commitment overdrawn status across all active construction projects."
  5. "Forward 12-month commitment exposure by trade."

Example outputs

Output — Weekly pipeline tracker (abridged, week ending 2026-04-10)

Pipeline stage summary.

| Stage | Count | YoY change |

|---|---|---|

| Under contract | 4 | flat |

| In entitlement | 2 | flat |

| In design | 3 | +1 |

| In permitting | 2 | -1 (Willow Creek advanced to construction) |

| In construction — mobilization | 1 | flat |

| In construction — foundation | 2 | flat |

| In construction — framing | 1 | flat |

| In construction — mep_rough | 2 | flat |

| In construction — drywall | 1 | flat |

| In construction — finishes | 2 | flat |

| In construction — punchlist | 1 | flat |

Schedule posture. Portfolio milestone_slippage_rate within band. Three

projects with schedule_variance_days outside band; one (Willow Creek) on

critical path with critical_path_slip_days (proposed) at overlay tolerance

ceiling. Hand off triggered to workflows/schedule_risk_review.

Cost posture. Portfolio capex_spend_vs_plan within band. Two projects

show contingency_burn_rate approaching 1.0 at percent-complete below 50%.

Hand off triggered to workflows/cost_to_complete_review. Portfolio

change_orders_pct_of_contract within overlay band; one project (Riverbend) at

edge.

Commitment exposure. Forward 12-month

commitment_exposure_forward_dollars (proposed) aggregated. Two commitments

failed pc_recon_commitment_overdrawn on Riverbend sitework contract — runbook

pointer surfaced. Draws on Riverbend held until resolved.

Draw posture. Portfolio draw_cycle_time trailing within band. One project

with open draw approved-not-funded past overlay (lender callback). Routed to

workflows/draw_package_review.

Delivery outlook. One project (South Fork) in the last 180 days before

expected TCO. Gating items: model-unit finishes, staffing plan signed. Hand off

to workflows/lease_up_first_period queued for next week.

Reconciliation posture. dp_handoff_dev_lag warning on one closed deal

(Atlantic Grove) — procore project not yet created, 7 business days since

funding; below blocker threshold but outside tolerance. Development_manager

notified.

Regional / deal-lead rollup. Southeast carries 6 of 11 active construction

projects. Alex's book carries 3 projects; weighted schedule slip within band.

Top-3 watch items.

  1. Willow Creek critical-path slip — schedule_risk_review triggered.
  2. Riverbend commitment overdrawn — draws held; runbook triggered.
  3. Atlantic Grove handoff lag — procore project creation expected within 3

business days.

Confidence banner.

References: dev_project_crosswalk@2026-04-08 (starter),
construction_duration_assumptions__southeast@2026-03-31 (starter),
reconciliation_tolerance_band@2026-03-31 (sample),
contingency_assumptions__{org}@2026-03-31 (starter).
Source-of-truth matrix: wave_4_authoritative.
Proposed metrics flagged: critical_path_slip_days, draw_burn_rate_vs_plan,
cco_to_first_lease_days, handoff_lag_dealpath_to_procore,
commitment_exposure_forward_dollars.