Delivery Handoff
Workflow purpose
Turn a Procore construction project at TCO/CO into an operating, leasable
asset with auditable handoff completion across AppFolio (operating),
Intacct (financial closeout), master data crosswalks (data platform), the
vendor master (construction subs out, operating service vendors in), and the
warranty + as-built documentation registry. The workflow does not execute
setup steps in vendor systems; it composes the handoff checklist, validates
each item's completion against the source-of-truth matrix, and routes gated
items through workflows/owner_approval_routing. Handoff is not complete
until every item is within the tolerance band on
reconciliation_tolerance_band.yaml and development_lead has signed off.
On completion, workflows/lease_up_first_period is triggered to pick up
the first operating period for the newly-active property.
Trigger conditions
- Explicit: "delivery handoff for {project}", "open delivery handoff package for {property}", "close the delivery handoff for {dev_project}", "handoff status for {project}".
- Implicit: Procore
schedule_milestonefirestemp_co_receivedorfinal_co_receivedANDunits_ready_for_lease >= 1(Handoff 8 inreference/connectors/_core/stack_wave4/lifecycle_handoffs.md). Alternatively, AppFolio records a C/O for a property currently atlifecycle_stage=pre_takeoverorconstruction. Either trigger activates the same workflow instance. - Recurring: none. Strictly event-driven.
Inputs (required / optional)
| Input | Type | Required | Notes |
|---|---|---|---|
| Procore project record (at or past TCO) | record | required | must include construction_project_id, dev_project_id (parent), schedule_milestone (temp_co_received or final_co_received), punchlist_items[], closeout_documents[], retainage_release_schedule, warranty_package_ref, as_built_package_ref |
| Canonical development_project, construction_project, capex_project objects | records | required | per source_of_truth_matrix.md: procore primary for construction_project; dealpath seeded development_project |
| AppFolio property record (at pre_takeover or equivalent) | record | required | reserved property_id from earlier post_ic_property_setup (if applicable) or dev-specific setup |
| Unit roster (as-built) | table | required | must match construction drawings exactly; unit_count_total, unit_count_rentable, nrsf_total populated per unit |
| Lease-up pricing policy draft | record | required | pricing policy + concession band for opening lease-up; ties into workflows/market_rent_refresh |
| Retainage release schedule | record | required | trade, amount held, release trigger, target release date |
| Warranty package | package | required | GC warranty, manufacturer warranties, effective dates, start-date triggers |
| As-built documentation package | package | required | drawings, specifications, systems manuals, commissioning reports |
| Construction sub vendor list | list | required | subs to be archived / flagged as non-operating |
| Operating service vendor list | list | required | new operating vendors to be onboarded (turf, pest, pool, waste, HVAC service, etc.) |
| Capex closeout package | package | required | final cost ledger, change-order summary, retainage status, contingency closeout |
| Handoff-lag tolerance band | yaml | required | from reference/normalized/schemas/reconciliation_tolerance_band.yaml |
| Approver roster | yaml | required | resolved per org overlay |
Outputs
| Output | Type | Shape |
|---|---|---|
| Delivery handoff checklist | handoff_checklist | per-item status (complete, in_progress, blocked, waived_with_approval) with owner, due-date, tolerance-band check |
| Delivery completeness scorecard | kpi_review | delivery_handoff_completeness_score (proposed) + per-workstream completion % + lag days |
| Blocker memo | memo | narrative with cited blocker ids and source-of-truth matrix references |
| Crosswalk row draft / closure | record | proposed property_master_crosswalk.yaml transition (pre_takeover -> lease_up), dev_project_crosswalk.yaml closure (procore_project_id -> property_id linkage), capex_project_crosswalk.yaml closeout, vendor_master_crosswalk.yaml additions/retirements |
| ApprovalRequest: handoff sign-off | record | row 7 if lag exceeds band; otherwise a terminal sign-off |
| Unresolved exception list | checklist | items routed to master_data/unresolved_exceptions_queue.md |
| lease_up_first_period trigger payload | record | event payload consumed by workflows/lease_up_first_period on completion |
Required context
asset_class, segment, form_factor, lifecycle_stage (development or construction at trigger, transitioning to lease_up), management_mode, market, property_id, construction_project_id, dev_project_id, org_id. jurisdiction required for C/O recording and any permitting signoffs.
Process
- Receive delivery trigger. Consume the Procore TCO/CO milestone (
temp_co_receivedorfinal_co_receivedwithunits_ready_for_lease >= 1) per Handoff 8 inlifecycle_handoffs.md. Alternatively consume the AppFolio C/O record for the property. If both arrive, reconcile viastack_reconciliation_matrix.md::recon_pc_to_af_at_delivery. If neither trigger is valid, refuse. - Load baseline. Pull canonical
development_project,construction_project,capex_project, placeholderproperty, and the unit roster drafted from construction drawings. Persource_of_truth_matrix.md, Procore is primary forconstruction_projectandschedule_milestone; AppFolio is primary forpropertyonce operating. - TCO/CO recording. Verify the certificate of occupancy has been received and recorded in AppFolio. If only temp CO is in hand, classify the handoff as
partial_deliveryand run inpartial_mode_behavioruntil final CO recorded. - Punchlist state review. Read the Procore punchlist; compute
punchlist_closeout_rate(existing; see_core/metrics.md). Outstanding p1/p2 punchlist items block operating handoff for units with those items; citepunchlist_sla__middle_market.csvfor SLA band. - Retainage release schedule. Confirm the retainage release plan per trade, target release date, and trigger condition. Compute
retainage_release_lag_days(proposed). Outside-band items flagged for reporting_finance_ops_lead. - Rent-roll transition. Move the AppFolio unit roster from the lease-up plan (hypothetical units per development) to active (real units available for lease). Unit count must match construction drawings exactly per
appfolio_pms.dq_rules.yaml::ap_lease_up_setup_complete. Mismatch is ablocker. - Vendor rationalization (construction subs vs operating service vendors). For each construction sub: confirm archived / flagged as non-operating in
vendor_master_crosswalk.yaml. For each new operating vendor: run identity resolution permaster_data/identity_resolution_framework.md; emit proposed additions or merges. Count goes tovendor_rationalization_count(proposed, shared withacquisition_handoff). - Warranty package handoff. Read the warranty package; confirm GC warranty start date + manufacturer warranties + effective windows are all captured. Track
warranty_package_completeness(proposed). Missing warranty items escalate via row 17. - System as-built documentation. Confirm drawings, specifications, systems manuals, commissioning reports are in the docs registry. Track
as_built_doc_completeness(proposed). Incomplete packages escalate viareporting_finance_ops_lead. - Capex project closeout in Intacct. Verify final cost ledger, change-order summary, retainage status, and contingency closeout are posted in Intacct per
source_of_truth_matrix.mdrowcapex_project: procore for scope/commitments; intacct for posted spend. Trackcapex_closeout_lag_days(proposed). Row 11 approval required for major capex closeout. - dev_project_crosswalk closure. Close the
dev_project_crosswalk.yamlrow by linkingprocore_project_id -> property_id; persurvivorship_rules.md::dev_project_default. Trackdev_project_crosswalk_closure_lag_days(proposed). - property_master_crosswalk transition. Propose the
lifecycle_stagetransition (pre_takeoverorconstruction->lease_up) inproperty_master_crosswalk.yaml. Proposed rows are staged and only merged after approval; seesurvivorship_rules.md. - Lease-up pricing policy seeded. Confirm the opening lease-up pricing policy has been seeded via
workflows/market_rent_refreshor equivalent. Required approval gate beforelease_up_first_periodcan run. - Handoff-lag screen. Compute
tco_to_first_unit_ready_days(proposed),cco_to_first_lease_days(proposed), and per-workstream lag againsthandoff_lag_threshold_daysfromreconciliation_tolerance_band.yaml. Any breach routes toworkflows/owner_approval_routingrow 7. - Completeness score. Compose
delivery_handoff_completeness_score(proposed) as weighted completion of the checklist (weights per overlay). - Sign-off packet. Assemble the development_lead sign-off packet with the checklist, scorecard, blocker memo, and crosswalk drafts. Route via
workflows/owner_approval_routingrow 7. - Trigger
lease_up_first_period. On final sign-off, emit the event payload forworkflows/lease_up_first_periodto pick up the first operating period for the now-active property. - Confidence banner. Surface
as_of_dateandstatustags for every reference file and crosswalk referenced; cite thelifecycle_handoffs.mdhandoff id for Handoff 8.
Metrics used
cco_to_first_lease_days(proposed: true) — days from final CO recording to first executed lease on the property;grain=property, unit=days,time_basis=event_stamped.tco_to_first_unit_ready_days(proposed: true) — days from temp CO to first unit marked ready-to-lease in AppFolio;grain=property, unit=days.delivery_handoff_completeness_score(proposed: true) — weighted completion of the delivery handoff checklist;grain=property,time_basis=as_of_date.punchlist_closeout_rate(existing; see_core/metrics.md) — percent of punchlist items closed at handoff;grain=project.retainage_release_lag_days(proposed: true) — days between release trigger met and actual release;grain=project, unit=days.warranty_package_completeness(proposed: true) — percent of required warranty docs on file;grain=property, unit=percent.as_built_doc_completeness(proposed: true) — percent of required as-built docs on file;grain=property, unit=percent.vendor_rationalization_count(proposed: true) — count of vendor master rows rationalized at delivery handoff (construction subs archived + operating vendors onboarded);grain=property.capex_closeout_lag_days(proposed: true) — days between final sign-off target and capex closeout posted in Intacct;grain=project, unit=days.dev_project_crosswalk_closure_lag_days(proposed: true) — days between delivery trigger anddev_project_crosswalk.yamlrow closure;grain=project, unit=days.lease_up_pace_post_delivery(existing; see_core/metrics.md) — units leased per week after TCO; surfaced as the downstream handoff metric intolease_up_first_period.
Proposed metrics will be lifted into _core/metrics.md in a dedicated change-log entry before the workflow is promoted beyond draft.
Reference files used
reference/connectors/_core/stack_wave4/lifecycle_handoffs.md— handoff definitions (Handoff 8).reference/connectors/_core/stack_wave4/source_of_truth_matrix.md— primacy rules fordevelopment_project,construction_project,capex_project,property,schedule_milestone.reference/connectors/_core/stack_wave4/stack_reconciliation_matrix.md—recon_pc_to_af_at_deliveryblocker-severity check.reference/connectors/adapters/procore_construction/manifest.yaml,dq_rules.yaml,reconciliation_checks.yaml— source shape;pc_to_af_handoffcheck cited.reference/connectors/adapters/appfolio_pms/manifest.yaml,dq_rules.yaml—ap_lease_up_setup_completerule cited.reference/connectors/adapters/sage_intacct_gl/manifest.yaml— GL primary for capex posted spend and closeout.reference/connectors/adapters/dealpath_deal_pipeline/manifest.yaml— Dealpath governance signoffs for development project.reference/connectors/master_data/property_master_crosswalk.yaml,dev_project_crosswalk.yaml,capex_project_crosswalk.yaml,vendor_master_crosswalk.yaml— crosswalks the workflow proposes rows for / closes.reference/connectors/master_data/identity_resolution_framework.md,survivorship_rules.md— identity and survivorship policy (specificallydev_project_defaultandcapex_project_default).reference/normalized/schemas/reconciliation_tolerance_band.yaml— handoff-lag bands.reference/normalized/approval_threshold_defaults.csv— approval thresholds (rows 4, 7, 11, 17, 19).reference/normalized/punchlist_sla__middle_market.csv— punchlist SLA band for p1/p2 items at delivery.
Escalation points
- Handoff lag. Any workstream exceeding
handoff_lag_threshold_daysescalates todevelopment_lead -> asset_mgmt_directorand opensapproval_requestrow 7. - Missing required approver. If the development_lead sign-off cannot be routed (role vacant per approver roster), escalates per row 17.
- Vendor master conflict. Unresolved duplicate or survivorship conflict goes to
master_data/unresolved_exceptions_queue.mdand routes to row 19. - Warranty package incomplete. Missing warranty documentation escalates to
development_lead + legal counselper row 17. - TCO before punchlist complete. Temp CO received while p1/p2 punchlist items are open on units proposed for lease. Escalates to
development_lead + construction_managerper row 4 (safety-critical maintenance decision). Workflow runs inpartial_mode_behavior. - Capex closeout drift. Major capex closeout posting lag in Intacct beyond band routes to
reporting_finance_ops_leadper row 11 (change-order threshold class). - Doc package incomplete. As-built package below completeness threshold routes to
reporting_finance_ops_lead.
Required approvals
development_lead_handoff_signoff— terminal approval that marks delivery handoff complete. Required for every delivery. Row 7 policy.capex_project_closeout_in_intacct— row 11 (major CO / capex closeout) for the final capex posting in Intacct.warranty_package_acceptance— row 17 (policy-marked, legal review of warranty terms prior to acceptance).lease_up_pricing_policy_seeded— row 13 (pricing policy above / at policy) for the opening lease-up pricing structure.- Crosswalk row transitions and closures (property_master, dev_project, capex_project, vendor_master): routed via
workflows/owner_approval_routingpersurvivorship_rules.md.
Failure modes
- Silent lifecycle_stage advance. Property flipped to
lease_upin AppFolio without Procore TCO/CO primacy confirmation. Fix:recon_pc_to_af_at_deliveryis a blocker-severity check; workflow halts on mismatch. - Unit roster mismatch. AppFolio unit roster differs from construction drawings. Fix:
ap_lease_up_setup_completedq rule gates; refuse until reconciled. - Punchlist ignored. Operating handoff marked complete while p1/p2 items open on proposed-lease units. Fix: workflow refuses unit-by-unit handoff for affected units; escalates via row 4.
- Warranty package incomplete. Delivery marked complete without warranty coverage in docs registry. Fix: conditional required input;
warranty_package_acceptanceapproval gate. - Capex closeout drift. Capex project closed in Procore but not posted in Intacct. Fix:
capex_closeout_lag_daystracked; row 11 approval required. - dev_project_crosswalk left open. Row never closes; procore_project_id and property_id never linked in canonical crosswalk. Fix: closure is a mandatory checklist item.
- Construction subs not archived. Construction subs remain active in operating vendor master. Fix: vendor rationalization step is required;
vendor_master_conflictescalation. - Operating vendors not onboarded. Handoff complete but no operating service vendors on file. Fix: operating vendor list is a required input; gap surfaces in handoff checklist.
- Stale confidence banner.
as_of_datereferences older than the TCO/CO date without acknowledgement. Fix: banner required per overlay staleness rule. - lease_up_first_period triggered prematurely. Downstream workflow fires before sign-off completes. Fix: trigger is gated on terminal sign-off.
Edge cases
- Late deal close. Not applicable (delivery is a development event, not an acquisition event). For acquisition path late close see
workflows/acquisition_handoff. - Multi-asset deal split. For development, one deal spawns one or more properties. The workflow opens one delivery-handoff instance per property delivered; parent
development_projectcarries union status across siblings. - Dev TCO before punch list complete. The workflow runs in
partial_mode_behavior. TCO-proven units with no open p1/p2 items may be marked ready-to-lease; other units remain pre-lease until punchlist closed.tco_to_first_unit_ready_dayscomputed on first-ready unit. - Partial delivery. Phase-1 delivery ahead of phase-2: one delivery handoff per phase;
property_master_crosswalkrow updateslifecycle_stageonly for the unit set delivered.dev_project_crosswalkclosure deferred until final phase delivery unlesssurvivorship_rules.md::dev_project_phase_closureallows per-phase close. - Vendor master not rationalized. Delivery proceeds for operating rent-roll activation while vendor rationalization remains
in_progress;vendor_rationalization_counttracks. Sign-off allowed only if rationalization deferred via row 19 waiver. - Crosswalk row not created on time.
dev_project_crosswalk_closure_lag_daysbreach triggers data-platform escalation; the workflow refuses final sign-off. - Lender notification missed. Lender construction-to-permanent conversion is a distinct workflow; delivery handoff only emits the operating-property readiness signal. A missing lender conversion flag on the dev_project_crosswalk row routes to
reporting_finance_ops_lead. - Insurance gap during transition. Builder's risk policy ending vs. operating property policy effective date. Mid-handoff gap triggers immediate row 17 escalation; rent-roll activation halts for any insurance-dependent checklist item.
- PMA execution lag. Not applicable to delivery (PMA, if TPM, executed at acquisition or dev-deal activation).
- property_master_crosswalk row not merged. If a proposed transition row conflicts with an existing canonical_id or the review is stalled, the item lands in
master_data/unresolved_exceptions_queue.mdwithreviewer: regional_ops_director. - Final CO delayed past temp CO by >band. The workflow escalates via row 4; partial operating handoff may continue for already-TCO'd units.
- Warranty start-date ambiguity. If GC warranty and manufacturer warranties have different start-date triggers (e.g., substantial completion vs. individual-unit completion), escalate to legal per row 17.
- Capex overrun at closeout. Final posted spend > approved budget + contingency. Row 11 approval gate required before closeout can be marked complete.
Example invocations
- "Run the delivery handoff for dev_project dev_chs_010_gu_2024 (Greystone Commons). Temp CO received 2026-04-02."
- "Status of the Greystone delivery handoff — flag any items outside the lag band."
- "Open the handoff sign-off packet for the development_lead for project dev_chs_010_gu_2024."
Example outputs
Output — Delivery handoff checklist (abridged, Greystone Commons dev_chs_010_gu_2024)
Handoff id. Handoff 8 per lifecycle_handoffs.md.
TCO/CO recording. complete. Temp CO recorded 2026-04-02; final CO targeted 2026-04-30. Partial mode while final CO pending.
Punchlist state. in_progress. punchlist_closeout_rate=87%. All p1/p2 items closed on the first 24 units proposed for lease; other units carry minor cosmetic items.
Retainage release schedule. complete. Per-trade schedule on file; retainage_release_lag_days=2 (within band).
Rent-roll transition. complete. AppFolio unit roster activated for the 24 TCO'd units; remaining 48 units staged. ap_lease_up_setup_complete check passed for the TCO'd set.
Vendor rationalization. in_progress. 9 construction subs archived; 7 of 11 operating vendors onboarded. vendor_rationalization_count=16 (9 archived + 7 onboarded).
Warranty package. complete. GC warranty + 12 manufacturer warranties on file; all start dates captured. warranty_package_completeness=100%.
As-built documentation. complete. Drawings, specs, systems manuals, commissioning reports in registry. as_built_doc_completeness=98% (one minor spec pending).
Capex closeout in Intacct. in_progress. Final cost ledger posted; contingency closeout pending row 11 approval. capex_closeout_lag_days=5.
dev_project_crosswalk closure. in_progress. procore_project_id -> property_id linkage drafted; pending reviewer approval. dev_project_crosswalk_closure_lag_days=3.
property_master_crosswalk transition. in_progress. Draft row transitioning lifecycle_stage from pre_takeover to lease_up for the TCO'd unit set; pending approval.
Lease-up pricing policy seeded. complete. Seeded via workflows/market_rent_refresh; row 13 approval on file.
Handoff completeness score. delivery_handoff_completeness_score=0.86.
Lag days. tco_to_first_unit_ready_days=3; cco_to_first_lease_days=n/a (final CO pending).
Open blockers. Operating vendor identity resolution for 4 rows; property_master_crosswalk + dev_project_crosswalk reviewer approval; capex contingency closeout row 11.
ApprovalRequest. Terminal sign-off packet assembled; routed to development_lead via workflows/owner_approval_routing row 7.
lease_up_first_period trigger. Gated on terminal sign-off; payload staged.
Confidence banner. dev_project_crosswalk@2026-03-31 (sample); capex_project_crosswalk@2026-03-31 (sample); property_master_crosswalk@2026-03-31 (sample); vendor_master_crosswalk@2026-03-31 (sample); source_of_truth_matrix@wave_4_authoritative; stack_reconciliation_matrix@wave_4_authoritative; reconciliation_tolerance_band@2026-03-31 (starter); procore_construction@wave_4 (stub); appfolio_pms@wave_4 (stub); punchlist_sla__middle_market@2026-03-31 (starter). Blocking rules cited: recon_pc_to_af_at_delivery, ap_lease_up_setup_complete, pc_to_af_handoff (none fired as blocker; one confidence-reduced in partial-mode on final CO pending).