Cost to complete review is an AI agent skill from the GitHub repository mariourquia/cre-skills-plugin. Recomputes cost-to-complete from current actuals plus remaining scope plus overlay-derived escalation and contingency. Compares against prior CTC and the underwriting baseline. Identifies the driver (labor, material, scope, duration) and recommends remediation (re-estimate, scope trim, re-bid, conti

How to use this skill

Skill file

Cost-to-Complete Review

Workflow purpose

Build an accurate, transparent cost-to-complete at any point in the project. Trigger remediation when CTC deviates from plan.

Trigger conditions

Inputs (required / optional)

| Input | Type | Required | Notes |

|---|---|---|---|

| Cost-to-date | record | required | from draw or GL |

| Approved COs | table | required | |

| Pending COs | table | required | scenario view |

| Remaining scope | table | required | assemblies, percent complete |

| Schedule update | record | required | for duration-based escalation |

| Prior CTC | record | required | for delta |

| Estimator baseline | estimate | required | |

Outputs

| Output | Type | Shape |

|---|---|---|

| CTC refresh | kpi_review | per trade, per project |

| Driver decomposition | table | labor / material / scope / duration |

| Contingency posture | kpi_review | remaining vs. plan |

| Scenario set | table | base / upside / downside |

| Recommendation memo | memo | remediation and approval path |

Required context

Asset_class, segment, form_factor, market, project.

Process

  1. Inherit cost to date. From most recent draw or GL.
  2. Compute remaining cost. Remaining scope x unit costs from library; market-adjust via labor/material references; apply escalation per overlay to expected execution dates per schedule.
  3. Apply contingency. Remaining scope contingency per overlay.
  4. Delta vs. prior CTC. Attribute to labor, material, scope, duration, CO.
  5. Scenario set. Base, upside (favorable buyouts, scope value engineering), downside (labor shortage, material spike, additional COs).
  6. Recommendation. If CTC within overlay, monitor. If above threshold, recommend remediation: re-estimate, scope trim, re-bid, contingency pull. Any budget reallocation above threshold opens approval.
  7. Confidence banner. References surfaced.

Metrics used

cost_to_complete, contingency_remaining, contingency_burn_rate, change_orders_pct_of_contract, schedule_variance_days.

Reference files used

Escalation points

Required approvals

Failure modes

  1. CTC without escalation. Fix: overlay escalator applied by execution date.
  2. CTC without scenario set. Fix: scenario set mandatory.
  3. Silent contingency pull. Fix: contingency posture explicit.
  4. Ignoring pending COs. Fix: scenario view includes pending.
  5. Sample library used as authoritative. Fix: confidence banner surfaces status.

Edge cases

Example invocations

  1. "Run the April CTC for Willow Creek."
  2. "Pressure-test CTC on the South End renovation."
  3. "Compare CTC to underwriting baseline for Riverbend."

Example outputs

Output — CTC refresh (abridged, Willow Creek April)

Cost to date. Inherited.

Remaining cost. Market-adjusted, escalated.

Contingency. Applied per overlay; remaining within band.

Delta vs. prior CTC. Attributed: material drift on two line items; labor hours above baseline on one.

Scenario set. Base within overlay. Downside approaches contingency exhaustion if labor shortage persists.

Recommendation. Monitor; re-estimate two line items at next draw; no reallocation needed.

Confidence banner. capex_line_items@2026-03-31 (starter), labor_rates__charlotte@2026-03-31 (sample), material_costs__southeast_residential@2026-03-31 (sample).