Cost-to-Complete Review
Workflow purpose
Build an accurate, transparent cost-to-complete at any point in the project. Trigger remediation when CTC deviates from plan.
Trigger conditions
- Explicit: "run CTC", "cost-to-complete refresh", "pressure-test the remaining budget".
- Implicit:
workflows/draw_package_reviewfinds CTC drift;workflows/change_order_reviewproduces material cost delta; milestone slippage from schedule. - Recurring: monthly per active project; re-run when a CO is reviewed.
Inputs (required / optional)
| Input | Type | Required | Notes |
|---|---|---|---|
| Cost-to-date | record | required | from draw or GL |
| Approved COs | table | required | |
| Pending COs | table | required | scenario view |
| Remaining scope | table | required | assemblies, percent complete |
| Schedule update | record | required | for duration-based escalation |
| Prior CTC | record | required | for delta |
| Estimator baseline | estimate | required | |
Outputs
| Output | Type | Shape |
|---|---|---|
| CTC refresh | kpi_review | per trade, per project |
| Driver decomposition | table | labor / material / scope / duration |
| Contingency posture | kpi_review | remaining vs. plan |
| Scenario set | table | base / upside / downside |
| Recommendation memo | memo | remediation and approval path |
Required context
Asset_class, segment, form_factor, market, project.
Process
- Inherit cost to date. From most recent draw or GL.
- Compute remaining cost. Remaining scope x unit costs from library; market-adjust via labor/material references; apply escalation per overlay to expected execution dates per schedule.
- Apply contingency. Remaining scope contingency per overlay.
- Delta vs. prior CTC. Attribute to labor, material, scope, duration, CO.
- Scenario set. Base, upside (favorable buyouts, scope value engineering), downside (labor shortage, material spike, additional COs).
- Recommendation. If CTC within overlay, monitor. If above threshold, recommend remediation: re-estimate, scope trim, re-bid, contingency pull. Any budget reallocation above threshold opens approval.
- Confidence banner. References surfaced.
Metrics used
cost_to_complete, contingency_remaining, contingency_burn_rate, change_orders_pct_of_contract, schedule_variance_days.
Reference files used
reference/normalized/capex_line_items__{scope}.csvreference/normalized/labor_rates__{market}.csvreference/normalized/material_costs__{region}_residential.csvreference/derived/contingency_assumptions__{org}.csvreference/normalized/construction_duration_assumptions__{region}.csvreference/normalized/approval_threshold_defaults.csv
Escalation points
- CTC variance above overlay threshold: CM -> AM -> executive.
- Contingency exhaustion risk: CM + AM approval request per overlay.
- Budget reallocation above threshold: approval row per overlay.
Required approvals
- Budget reallocation above threshold.
Failure modes
- CTC without escalation. Fix: overlay escalator applied by execution date.
- CTC without scenario set. Fix: scenario set mandatory.
- Silent contingency pull. Fix: contingency posture explicit.
- Ignoring pending COs. Fix: scenario view includes pending.
- Sample library used as authoritative. Fix: confidence banner surfaces status.
Edge cases
- Late-stage value engineering: scope trim may offset CTC drift; document VE basis.
- Trade buyout mid-project: favorable or unfavorable buyout feeds CTC;
trade_buyout_variancereferenced. - Force-majeure delay: duration escalation significant; surface clearly.
- Multiple stacked COs: aggregate effect on CTC; stacked approval path.
Example invocations
- "Run the April CTC for Willow Creek."
- "Pressure-test CTC on the South End renovation."
- "Compare CTC to underwriting baseline for Riverbend."
Example outputs
Output — CTC refresh (abridged, Willow Creek April)
Cost to date. Inherited.
Remaining cost. Market-adjusted, escalated.
Contingency. Applied per overlay; remaining within band.
Delta vs. prior CTC. Attributed: material drift on two line items; labor hours above baseline on one.
Scenario set. Base within overlay. Downside approaches contingency exhaustion if labor shortage persists.
Recommendation. Monitor; re-estimate two line items at next draw; no reallocation needed.
Confidence banner. capex_line_items@2026-03-31 (starter), labor_rates__charlotte@2026-03-31 (sample), material_costs__southeast_residential@2026-03-31 (sample).