Construction Meeting Prep and Action Tracking
Workflow purpose
Reduce meeting time; increase meeting clarity. Produce the agenda, the data pack, and a clean action-item ledger. Follow up reliably.
Trigger conditions
- Explicit: "build the construction meeting pack", "agenda for OAC", "action item update".
- Implicit: scheduled meeting date approaching; open action items aging; new RFI or submittal.
- Recurring: weekly or biweekly per overlay.
Inputs (required / optional)
| Input | Type | Required | Notes |
|---|---|---|---|
| Prior meeting action items | table | required | open and closed |
| Current schedule state | record | required | |
| RFI and submittal log | table | required | |
| Open CO log | table | required | |
| Safety log | table | required | |
| Budget and CTC summary | record | required | |
Outputs
| Output | Type | Shape |
|---|---|---|
| Meeting agenda | checklist | topics, owner, time box |
| Data pack | memo | KPIs, schedule, budget, RFI, CO, safety |
| Action-item ledger update | table | status, owner, due date |
| Action-item reminders | email_draft | for stale items |
Required context
Asset_class, segment, form_factor, market, project.
Process
- Agenda compose. From overlay template + open items.
- Data pack compose. KPI rollup, schedule, budget, RFI, CO, safety.
- Action-item review. Close completed; age open; identify stale (past due).
- Reminder drafts. For each stale item, draft a reminder with owner and due-date nudge.
- Meeting follow-up. Post-meeting capture of new items and decisions.
- Confidence banner. References surfaced.
Metrics used
schedule_variance_days, milestone_slippage_rate, change_orders_pct_of_contract, cost_to_complete, punchlist_closeout_rate.
Reference files used
reference/normalized/approval_threshold_defaults.csv
Escalation points
- Stale action item: CM -> AM.
Required approvals
None by default; any decisions captured in meeting minutes that trigger approvals (e.g., scope change) route through relevant workflow.
Failure modes
- Meeting without action-item ledger. Fix: ledger is the backbone.
- Stale items never surfaced. Fix: aging view mandatory.
- Minutes without decisions captured. Fix: decisions separate from discussion in the data pack template.
Edge cases
- Absent owner for a critical item: escalate to next level in overlay.
- Item crossing multiple trades: cross-reference in ledger.
- Cancelled meeting: action-item cadence continues; asynchronous updates recorded.
Example invocations
- "Build the OAC pack for Willow Creek this Wednesday."
- "Stale action items across Riverbend construction."
- "Update the action ledger after Thursday's meeting."
Example outputs
Output — OAC meeting pack (abridged, Willow Creek)
Agenda. Safety, schedule, RFIs, submittals, COs, budget / CTC, punch, action items.
Data pack. KPI snapshot; schedule_variance_days and milestone_slippage_rate within band; RFI and submittal log counts; CO log with rows 10/11 status; safety log clean; CTC within overlay.
Action-item ledger. Closed 6 items; opened 3; aged 2 stale; reminder drafts prepared.
Confidence banner. approval_threshold_defaults@2026-03-31 (starter).