Change order review

From mariourquia/cre-skills-plugin · View interactive version

Change order review is an AI agent skill from the GitHub repository mariourquia/cre-skills-plugin. Reviews each proposed change order: validates scope basis, re-estimates cost, checks schedule impact, evaluates against contingency, recommends approval or rejection, and routes to the correct approval row by dollar threshold. Tracks `change_orders_pct_of_contract` and `contingency_burn_rate`.

How to use this skill

Skill file

Change Order Review

Workflow purpose

Convert a change order request into an informed decision with a cost, schedule, and contingency view. Route to the correct approval row. Keep the change-order trail clean for draw review and cost-to-complete.

Trigger conditions

Inputs (required / optional)

| Input | Type | Required | Notes |

|---|---|---|---|

| CO package | doc | required | narrative, line items, schedule |

| Original scope and contract | doc | required | basis |

| Prior COs | table | required | cumulative view |

| Estimator baseline | estimate | required | for re-estimate |

| Schedule record | record | required | for impact |

| Contingency status | derived | required | contingency_remaining, burn rate |

Outputs

| Output | Type | Shape |

|---|---|---|

| CO review memo | memo | scope, cost, schedule, contingency impact, recommendation |

| Updated contract value | record | with CO pending or approved state |

| Updated schedule | record | milestone impacts |

| Approval request | request | row 10 or 11 |

Required context

Asset_class, segment, form_factor, market, project.

Process

  1. Scope validation. Compare CO narrative to original contract and current scope; identify whether the change is scope add, deduct, credit, or clarification.
  2. Re-estimate. Apply library, labor, and material references; compare to GC's proposed cost.
  3. Schedule impact. Evaluate milestone impacts; compute schedule_variance_days delta.
  4. Contingency impact. Compute contingency_remaining and contingency_burn_rate after CO. If burn exceeds overlay band, flag.
  5. Decision recommendation. Approve / negotiate / reject based on scope rationale and cost variance.
  6. Approval routing. Row 10 for minor; row 11 for major. Thresholds overlay-driven.
  7. Safety-critical scope change. If change defers or modifies life-safety scope, row 4 also applies.
  8. Documentation. Update contract register, schedule register, change-order log.
  9. Confidence banner. References surfaced.

Metrics used

change_orders_pct_of_contract, contingency_remaining, contingency_burn_rate, cost_to_complete, schedule_variance_days.

Reference files used

Escalation points

Required approvals

Failure modes

  1. Approving without re-estimate. Fix: re-estimate mandatory.
  2. Missing schedule impact. Fix: schedule impact mandatory.
  3. Approving without contingency view. Fix: contingency impact mandatory.
  4. Treating scope clarification as added cost. Fix: scope validation classifies.
  5. Safety-scope deferral silent. Fix: row 4 gate.

Edge cases

Example invocations

  1. "Review the PCO submitted for Ashford Park amenity refresh."
  2. "CO log for the Willow Creek renovation program — anything trending hot?"
  3. "Evaluate this scope change request on Riverbend construction."

Example outputs

Output — CO review (abridged, amenity refresh PCO)

Scope. Scope add per owner direction; library mapping present.

Re-estimate. Cost within overlay range of GC proposal; negotiation lever identified in one line.

Schedule. No critical path impact; schedule_variance_days unchanged.

Contingency. contingency_remaining after CO within overlay band; contingency_burn_rate within tolerance.

Recommendation. Approve at negotiated line adjustment; approval_request row 10 opened.

Confidence banner. capex_line_items__amenity@2026-03-31, status=starter. contingency_assumptions@2026-03-31, status=starter.

Use this skill with your AI agent: Open on Skill Issue to copy, download, or add to your library. Works with Claude, ChatGPT, Gemini, Cursor, Windsurf and more.