Sprint Retro
Review the sprint outcome and capture lessons for next time.
When to Use
- "How did the sprint go?"
- "Let's do a retro"
- "What did we miss?"
- End of sprint or after the driving deadline event
- When something went wrong and you want to capture the lesson
Arguments
$ARGUMENTS can be:
- Empty — review the most recent sprint plan
- A path to a specific plan file
Workflow
Phase 1: Gather Evidence
- Read the sprint plan — what was planned, who was assigned what
- Read the dashboard —
docs/features/DASHBOARD.md— what actually shipped - Check git history —
git log --oneline --since="[sprint start]"— what actually landed - Check PR history —
gh pr list --state all --limit 30— what was opened, merged, closed
Phase 2: Planned vs. Actual
Build a comparison table:
| Feature | Planned | Actual | Notes |
|---------|---------|--------|-------|
| `feature-a` | Deadline-Critical | Shipped | On track |
| `feature-b` | This Sprint | In Progress | Took longer than expected — effort was Medium, needed Large |
| `feature-c` | This Sprint | Not Started | Blocked by AIDP cluster access |
| `feature-d` | Not Planned | Shipped | Emerged mid-sprint as a dependency |
Phase 3: Identify Patterns
Look for recurring themes:
Estimation accuracy:
- Were effort estimates (Small/Medium/Large) accurate?
- Which items took longer than expected? Why?
- Were any items easier than expected?
Blocking patterns:
- What blocked progress? (external teams, infrastructure, unclear specs, missing context)
- Could the blocks have been identified earlier?
- Did the dependency graph hold up, or were there surprise dependencies?
Spec quality:
- Did developers have to ask questions that should have been in the spec?
- Were any specs missing critical information?
- Did the spec audit (
/sprint-audit-specs) catch the gaps?
Assignment quality:
- Were tasks assigned to the right people?
- Did junior devs get stuck? On what?
- Were senior devs bottlenecked on too many critical-path items?
Phase 4: Capture Lessons
Format lessons as actionable rules:
## Lessons Learned
### What Worked
- [Specific thing that worked well and WHY]
- [Pattern to repeat next sprint]
### What Didn't Work
- [Specific problem and root cause]
- [What we'd do differently]
### Process Improvements
- [Concrete change to make next sprint]
- [E.g., "Add realistic data ranges to all data-generation specs"]
- [E.g., "Verify PR status with `gh pr view` before planning around it"]
### Estimation Calibration
- [Feature X was estimated Small, took Medium — reason: ...]
- [Adjust future estimates for similar work]
Phase 5: Update Plugin Memory
If lessons are broadly applicable (not project-specific), suggest adding them to the sprint-planner plugin itself:
- New checklist items for
/sprint-audit-specs - New anti-patterns for
/sprint-triage - New rules for
/sprint-plan
Present these as suggestions — don't auto-modify the plugin.
Output
Present the retro summary and ask:
- "Anything I missed?"
- "Should we capture any of these lessons in the plugin for next time?"
- "Ready to start planning the next sprint?"
Integration Notes
Works with:
/sprint-plan— lessons feed into the next sprint's planning/sprint-audit-specs— retro findings improve the audit checklist- feature-workflow plugin — reads DASHBOARD.md for shipped status