Roadmap backcast

From lyndonkl/claude · View interactive version

Roadmap backcast is an AI agent skill from the GitHub repository lyndonkl/claude. Plans backward from a fixed goal or deadline to the present, identifying required milestones, dependencies, critical path, and feasibility constraints to transform aspirational targets into actionable sequenced plans. Use when planning with fixed deadlines, working backward from future goals, mappin

How to use this skill

Skill file

Roadmap Backcast

Table of Contents

  1. Workflow
  2. Dependency Mapping
  3. Critical Path Analysis
  4. Common Patterns
  5. Guardrails
  6. Quick Reference

Workflow

Copy this checklist and track your progress:

Roadmap Backcast Progress:
- [ ] Step 1: Define target outcome precisely
- [ ] Step 2: Work backward to identify milestones
- [ ] Step 3: Map dependencies and sequencing
- [ ] Step 4: Identify critical path
- [ ] Step 5: Assess feasibility and adjust

Step 1: Define target outcome precisely

State specific outcome (not vague goal), target date, success criteria. See Common Patterns for outcome definition examples. For straightforward backcasts → Use resources/template.md.

Step 2: Work backward to identify milestones

Start at end, ask "what must be true just before this?" iteratively. Create 5-10 major milestones. For complex multi-year roadmaps → Study resources/methodology.md.

Step 3: Map dependencies and sequencing

Identify what depends on what, what can run in parallel. See Dependency Mapping for techniques.

Step 4: Identify critical path

Find longest sequence of dependent tasks (this determines minimum timeline). See Critical Path Analysis.

Step 5: Assess feasibility and adjust

Compare required timeline to available time. Add buffers (20-30%), identify risks, adjust scope or date if needed. Self-check using resources/evaluators/rubric_roadmap_backcast.json before finalizing. Minimum standard: Average score ≥ 3.5.

Dependency Mapping

Dependency types:

Sequential (A → B): B cannot start until A completes

Parallel (A ∥ B): A and B can happen simultaneously

Converging (A, B → C): C requires both A and B to complete

Diverging (A → B, C): A enables both B and C

Critical Path Analysis

Critical path: Longest sequence of dependent tasks (determines minimum project duration)

Finding critical path:

  1. List all milestones with durations
  2. Draw dependency graph (arrows from prerequisite to dependent)
  3. Calculate earliest start/finish for each milestone (forward pass)
  4. Calculate latest start/finish for each milestone (backward pass)
  5. Milestones with zero slack (earliest = latest) are on critical path

Example:

Milestone A (4 weeks) → Milestone B (6 weeks) → Milestone D (2 weeks) = 12 weeks (critical path)
Milestone A (4 weeks) → Milestone C (3 weeks) → Milestone D (2 weeks) = 9 weeks (non-critical, 3 weeks slack)

Critical path is 12 weeks (A→B→D path)

Managing critical path:

Common Patterns

Pattern 1: Product Launch with Fixed Date

Pattern 2: Compliance Deadline (Regulatory)

Pattern 3: Strategic Transformation (Multi-Year)

Pattern 4: Event Planning (Conference, Launch Event)

Guardrails

Feasibility checks:

Common pitfalls:

Quality standards:

Quick Reference

Resources:

5-Step Process: Define Target → Work Backward → Map Dependencies → Find Critical Path → Assess Feasibility

Dependency types: Sequential (A→B) | Parallel (A∥B) | Converging (A,B→C) | Diverging (A→B,C)

Critical path: Longest dependent sequence = minimum project duration

Buffer rule: Add 20-30% to estimates, 40%+ for high-uncertainty work

Feasibility test: Required time ≤ Available time (with buffer)