Cloud Migration
Purpose
Plan and execute cloud migrations using the 7 Rs strategy framework, with tools, testing, cutover planning, and post-migration optimization.
Agent Protocol
Trigger
"cloud migration", "migrate to cloud", "lift and shift", "rehost", "replatform", "7 Rs", "migration strategy", "AWS MGN", "Azure Migrate".
Input Context
Application inventory, dependencies, data volumes, downtime tolerance, target cloud, licensing constraints.
Output Artifact
Migration plan, wave schedule, cutover runbook. No file unless requested.
Response Format
Portfolio: {apps and chosen R (rehost|replatform|refactor|repurchase|relocate|retain|retire)}
Waves: {wave -> apps}
Tooling: {MGN|DMS|Azure Migrate|...}
Cutover: {strategy, downtime window, rollback}
Risks: {...}
Architecture Decision Trees
7 Rs Migration Strategies
| Strategy | Definition | Effort | Duration | Cloud Benefit |
|---|---|---|---|---|
| Retire | Decommission | Low | Short | Cost savings |
| Retain | Keep on-prem | None | N/A | None |
| Rehost (Lift-Shift) | Move as-is to IaaS | Low | Weeks-Months | Minimal (lower DC cost) |
| Replatform | Move to managed service | Medium | Months | Moderate |
| Refactor / Rearchitect | Rewrite for cloud-native | High | Months-Years | Maximum |
| Repurchase | Switch to SaaS | Medium | Weeks-Months | Functional improvement |
| Relocate | Move to hyperscaler DC | Low | Weeks | Lower latency |
Strategy Selection Decision
Is the application end-of-life?
├── Yes → Retire (decommission, cost savings)
└── No → Is it a SaaS replacement available?
├── Yes → Repurchase (SaaS switch)
└── No → Need cloud-native benefits (scalability, resilience)?
├── Yes → Can we rewrite the application?
│ ├── Yes → Refactor/Rearchitect (max benefit, max effort)
│ └── No → Replatform (managed services, moderate effort)
└── No → Immediate migration needed?
├── Yes → Rehost (fastest path to cloud)
└── No → Replatform or retain (take time to optimize)
Readiness Assessment
| Dimension | Assessment | Metrics |
|---|---|---|
| Technical | Architecture compatibility | OS, DB, dependency graph |
| Operational | Process maturity | Monitoring, backup, DR |
| Security | Compliance requirements | Encryption, IAM, audit logs |
| Financial | TCO analysis | Current vs cloud cost |
| Skills | Team readiness | Training needs assessment |
Discovery Tool Selection
| Tool | Scope | Platform | Data Collected |
|---|---|---|---|
| AWS MGN (Application Migration) | VMs | AWS | OS, apps, resources |
| Azure Migrate | VMs + databases | Azure | Dependency mapping |
| Google Migrate for Compute | VMs | GCP | Utilization, network |
| RVTools | VMware VMs | Any | VM config, storage |
| ServiceNow ITOM | Enterprise | Any | CMDB, dependencies |
| CloudHealth | Multi-cloud | Any | Cost, utilization |
| Faddom | App dependency | Any | Application dependency mapping |
| CloudEndure (now AWS MGN) | VMs | AWS | Continuous replication |
Migration Wave Planning
| Wave | Type | Risk | Duration | Max Workloads |
|---|---|---|---|---|
| Wave 0 | Foundation | Low | 2-4 weeks | N/A (infrastructure) |
| Wave 1 | Pilot (low-risk) | Low | 2 weeks | 3-5 workloads |
| Wave 2 | Early adopters | Low-Medium | 4 weeks | 10-15 workloads |
| Wave 3-N | Bulk migration | Medium | 4-6 weeks ea. | 20-50 workloads |
| Final Wave | Complex/high-risk | High | 4-8 weeks | 5-10 workloads |
Core Workflow
Step 1: Migration Assessment — TCO Analysis
# assessment/tco_analysis.py
"""Total Cost of Ownership comparison for on-prem vs cloud."""
import json
from dataclasses import dataclass, asdict
@dataclass
class WorkloadSpec:
name: str
vcpu: int
memory_gb: int
storage_gb: int
storage_type: str # HDD, SSD, NVMe
network_throughput: str # Mbps
licenses: list[str] # Windows, SQL, Oracle, etc.
def estimate_cloud_cost(self, provider="aws", region="us-east-1"):
"""Estimate monthly cloud cost."""
cost = 0
# Compute costs (example pricing)
if provider == "aws":
instance_map = {
(2, 4): "m6i.large",
(4, 16): "m6i.xlarge",
(8, 32): "m6i.2xlarge",
(16, 64): "m6i.4xlarge",
}
key = (self.vcpu, self.memory_gb)
instance = instance_map.get(key, "m6i.xlarge")
compute = {"m6i.large": 69, "m6i.xlarge": 138,
"m6i.2xlarge": 276, "m6i.4xlarge": 553}
cost += compute.get(instance, 138)
# Storage costs
storage_rates = {"HDD": 0.08, "SSD": 0.125, "NVMe": 0.25}
cost += self.storage_gb * storage_rates.get(self.storage_type, 0.125)
# License costs
license_rates = {"Windows": 50, "SQL": 300, "Oracle": 500}
for lic in self.licenses:
cost += license_rates.get(lic, 0)
return cost
def estimate_onprem_cost(self):
"""Estimate monthly on-prem cost (3-year amortized)."""
hardware = (self.vcpu * 200 + self.memory_gb * 15 + self.storage_gb * 2)
power_cooling = hardware * 0.3
admin = 1500 # shared admin overhead
return (hardware / 36) + power_cooling / 12 + admin
# Example
workload = WorkloadSpec("web-app", 4, 16, 200, "SSD", "1Gbps", ["Windows"])
onprem = workload.estimate_onprem_cost()
cloud = workload.estimate_cloud_cost()
print(f"Workload: {workload.name}")
print(f" On-prem: ${onprem:.0f}/mo")
print(f" Cloud: ${cloud:.0f}/mo")
Step 2: Database Migration — AWS DMS
# migration/dms.tf
resource "aws_dms_replication_subnet_group" "main" {
replication_subnet_group_description = "DMS subnet group"
subnet_ids = aws_subnet.private[*].id
}
resource "aws_dms_replication_instance" "main" {
replication_instance_class = "dms.c5.large"
replication_instance_id = "production-migration"
allocated_storage = 100
multi_az = true
publicly_accessible = false
vpc_security_group_ids = [aws_security_group.dms.id]
replication_subnet_group_id = aws_dms_replication_subnet_group.main.id
}
resource "aws_dms_endpoint" "source" {
endpoint_id = "source-onprem"
endpoint_type = "source"
engine_name = "postgres"
server_name = "192.168.1.100"
port = 5432
database_name = "production_db"
username = var.db_migration_user
password = var.db_migration_password
ssl_mode = "require"
extra_connection_attributes = "ParallelLoadThreads=4;ParallelLoadBufferSize=64"
}
resource "aws_dms_endpoint" "target" {
endpoint_id = "target-rds"
endpoint_type = "target"
engine_name = "postgres"
server_name = aws_db_instance.main.address
port = 5432
database_name = "production_db"
username = var.db_username
password = var.db_password
ssl_mode = "require"
}
resource "aws_dms_replication_task" "full_load" {
replication_task_id = "initial-load"
replication_instance_arn = aws_dms_replication_instance.main.replication_instance_arn
source_endpoint_arn = aws_dms_endpoint.source.endpoint_arn
target_endpoint_arn = aws_dms_endpoint.target.endpoint_arn
migration_type = "full-load-and-cdc"
table_mappings = jsonencode({
rules: [{
"rule-type": "selection"
"rule-id": "1"
"rule-name": "1"
"object-locator": {"schema-name": "public", "table-name": "%"}
"rule-action": "include"
}]
})
replication_task_settings = jsonencode({
FullLoadSettings: {
TargetTablePrepMode: "DROP_AND_CREATE",
CreatePkAfterFullLoad: true,
MaxFullLoadSubTasks: 8,
},
Logging: { EnableLogging: true }
})
}
Step 3: Cutover Plan Template
# migration/cutover-plan.yaml
migration_id: "MIG-2025-001"
workload: "Payment Processing System"
target_platform: "AWS (us-east-1)"
scheduled_date: "2025-06-15T02:00:00 UTC"
pre_cutover:
- task: "Final data sync check"
owner: "DBA-Team"
duration: 15m
- task: "Application shutdown"
owner: "App-Team"
duration: 5m
- task: "Final incremental backup"
owner: "DBA-Team"
duration: 10m
- task: "DNS TTL reduction (60s)"
owner: "NetOps"
duration: 5m
- task: "Scale up target environment"
owner: "CloudOps"
duration: 10m
cutover:
- task: "Start DMS CDC replication"
owner: "DBA-Team"
duration: 5m
- task: "Verify data consistency (row counts, checksums)"
owner: "DBA-Team"
duration: 15m
- task: "Stop source database writes"
owner: "DBA-Team"
duration: 2m
- task: "Apply final CDC changes"
owner: "DBA-Team"
duration: 5m
- task: "Promote target database"
owner: "DBA-Team"
duration: 2m
- task: "Update DNS to target load balancer"
owner: "NetOps"
duration: 2m
- task: "Start application on target"
owner: "App-Team"
duration: 5m
post_cutover:
- task: "Run smoke tests"
owner: "QA-Team"
duration: 15m
- task: "Verify monitoring/alerts on target"
owner: "CloudOps"
duration: 10m
- task: "Monitor error rates for 30 min"
owner: "App-Team"
duration: 30m
- task: "Declare cutover complete"
owner: "Migration-Lead"
duration: 2m
rollback_triggers:
- condition: "Application error rate > 5% for 5 minutes"
action: "Revert DNS to source; failback database"
- condition: "Database replication lag > 60s"
action: "Abort cutover; keep source as primary"
- condition: "Data consistency check fails"
action: "Investigate; abort if > 0.01% mismatch"
rollback:
- task: "Revert DNS to source IP"
duration: 2m
- task: "Re-enable source application"
duration: 5m
- task: "Verify source operation"
duration: 15m
- task: "Stop DMS replication"
duration: 2m
- task: "Notify stakeholders"
duration: 5m
Step 4: Migration Runbook
# Migration Runbook: Production Database
## Pre-Migration Checklist
- [ ] Source: PostgreSQL 15.3 on-prem (192.168.1.100:5432)
- [ ] Target: RDS PostgreSQL 15.4 (production-db.xxx.us-east-1.rds.amazonaws.com)
- [ ] DMS replication instance running (dms.c5.large)
- [ ] Full load completed successfully
- [ ] CDC replication lag < 5 seconds
- [ ] Application config updated for target DB endpoint
- [ ] Snapshot of target DB created
- [ ] Rollback plan reviewed and approved
- [ ] Stakeholders notified of maintenance window
## Cutover Commands
1. Stop source application
ssh app-server 'systemctl stop app-service'
2. Wait for CDC to catch up
aws dms describe-replication-tasks \
--filters Name=replication-task-id,Values=dms-full-load
3. Stop CDC replication
aws dms stop-replication-task \
--replication-task-arn arn:aws:dms:...
4. Verify target data
psql -h production-db.xxx.rds.amazonaws.com \
-c "SELECT count(*) FROM orders;"
5. Point the app at the target (DNS/connection-string switch, not a DB rename)
kubectl -n production set env deployment/app-service DATABASE_HOST=production-db.xxx.rds.amazonaws.com
6. Roll out with an immutable, reviewed image tag (never :latest)
kubectl -n production rollout status deployment/app-service
7. Verify
curl -f https://app.example.com/health
### Step 5: Large Data Transfer
Pick the transfer path from data volume and available bandwidth (time ≈ size / usable throughput):
- **Online** (preferred when the link allows): AWS DataSync, `aws s3 sync`, Azure AzCopy / Data Box Gateway, GCP Storage Transfer Service. Encrypt in transit, throttle during business hours, verify with checksums or object counts.
- **Offline appliances** for very large one-time loads: AWS Snow Family, Azure Data Box, Google Transfer Appliance. Availability and supported device types change; check the provider's current offering before planning around one.
- **Database data**: use the database engine's replication or a migration service (AWS DMS, Azure Database Migration Service, GCP Database Migration Service) so CDC keeps the target in sync until cutover.
Online example: incremental copy, then a verification pass with no transfer
aws s3 sync /data/large-dataset s3://migration-data/large-dataset/
aws s3 sync /data/large-dataset s3://migration-data/large-dataset/ --dryrun # should list nothing
### Step 6: Azure Migrate — Discovery and Assessment
1. Create an Azure Migrate project in the portal (or with Bicep/ARM).
2. Deploy the Azure Migrate appliance on-premises (VMware, Hyper-V or physical) to discover servers, dependencies and performance data.
3. Create a performance-based assessment (sizing on a percentile of collected utilization, target region, pricing options).
4. Replicate and migrate servers with the Migration and modernization tool; run a test migration into an isolated VNet before the real cutover.
### Step 7: GCP — Migrate to Virtual Machines
gcloud services enable vmmigration.googleapis.com
1. Register the source (vSphere via the Migrate Connector appliance, or AWS/Azure as sources) in the Migrate to Virtual Machines console.
2. Trust vCenter with its real CA certificate; do not disable TLS verification for the connector.
3. Group VMs into migration groups (waves), configure target project, zone, network and machine type.
4. Start replication, run a **test clone** into an isolated network, then cut over and keep the source powered off (not deleted) until validation completes.
### Step 8: Post-Migration Optimization
post_migration/optimize.py
"""Review post-migration for optimization opportunities."""
import boto3
def post_migration_review():
"""Check for replatforming opportunities."""
ec2 = boto3.client('ec2')
rds = boto3.client('rds')
# Check EC2 instances that could be Lambda
instances = ec2.describe_instances(
Filters=[{'Name': 'instance-state-name', 'Values': ['running']}]
)
for reservation in instances['Reservations']:
for instance in reservation['Instances']:
instance_type = instance['InstanceType']
# Flag t2.nano/micro/small as Lambda candidates
if instance_type in ['t2.nano', 't2.micro', 't2.small']:
print(f"Candidate for Lambda: {instance['InstanceId']} ({instance_type})")
# Check RDS instances for Aurora upgrade
db_instances = rds.describe_db_instances()
for db in db_instances['DBInstances']:
if 'mysql' in db['Engine'] and db['EngineVersion'].startswith('5'):
print(f"Candidate for Aurora MySQL: {db['DBInstanceIdentifier']}")
if 'postgres' in db['Engine'] and float(db['EngineVersion'][:2]) < 13:
print(f"Candidate for version upgrade: {db['DBInstanceIdentifier']}")
### Step 9: Migration Testing Strategy
┌────────────────────────────────────────────────────────┐
│ Migration Testing Pyramid │
├────────────────────────────────────────────────────────┤
│ │
│ /\ Smoke Tests (post-cutover) │
│ / \ - Health endpoints │
│ / \ - Critical user journeys │
│/__\ │
│──────── │
│ || Data Validation │
│ || - Row counts match │
│ || - Checksum verification │
│ || - Referential integrity │
│──────── │
│ || Performance Tests │
│ || - Latency comparison │
│ || - Throughput benchmarks │
│ || - Connection pool sizing │
│──────── │
│ || Functional Tests │
│ || - API contract tests │
│ || - Integration tests │
│ || - Authorization/authentication │
│──────── │
│ || Dry Run Tests │
│ || - Full migration in staging │
│ || - Timed cutover rehearsal │
│ || - Rollback procedure test │
└────────────────────────────────────────────────────────┘