Modeling construction period risk is an AI agent skill from the GitHub repository CaseMark/skills. Analyzes construction risk with EPC contract review, delay and cost overrun scenarios, and completion guarantee structures. Use when modeling construction risk, evaluating EPC terms, or stress testing project timelines.
Funding plan — equity/debt split, draw schedule, construction facility terms (commitment fees, margin during construction), equity contribution agreement timing
Contractor profile — EPC contractor credit rating, track record on comparable projects, bonding capacity, subcontractor reliance
Insurance program — builder's risk, delay-in-startup (DSU/ALOP) coverage, deductibles, sub-limits
Site/permitting status — land acquisition status, environmental permits, interconnection agreements, offtake contract conditions precedent [VERIFY: jurisdiction-specific permitting requirements]
Workflow
Map the EPC risk allocation — Extract key risk provisions from the EPC contract: price structure (lump-sum turnkey vs. open-book), LD caps (typical range: 15-20% of contract price for aggregate LDs), warranty scope, defect liability period, and carve-outs from contractor liability (force majeure, owner-caused delays, change-in-law)
Build the construction cost model — Structure total project cost as: EPC price + owner's costs + development fees + financing costs (IDC + fees) + contingency. Model contingency drawdown assumptions. Separate hard costs from soft costs. Flag any cost items outside the EPC wrap [VERIFY: treatment of sales tax/VAT on construction costs by jurisdiction]
Model the draw schedule — Create monthly or quarterly construction draw curves. Standard S-curve or milestone-based draws tied to EPC payment schedule. Layer in equity-first vs. pro-rata vs. debt-first contribution mechanics. Calculate IDC based on drawn balances and construction facility pricing
Run delay scenarios — Model 3-6-12 month delay cases:
Revenue impact: lost operating cash flow during delay period
Validate that completion guarantee coverage matches or exceeds modeled worst-case funding gap
Cross-check construction facility commitment amount against peak draw requirement plus headroom
Confirm all cost and schedule assumptions are sourced (independent engineer report, EPC contract, or sponsor estimate) — mark unsourced items with [VERIFY]
Flag any scenario where the project cannot reach financial completion under stress without additional uncommitted support