Azure Cloud Migrate
Migrate workloads to Azure in controlled waves with clear risk management, rollback options, and validation.
Use This Skill When
- The user is moving applications or data to Azure
- The user needs migration planning and wave sequencing
- The user needs cutover and post-migration validation
- The user wants to assess workload readiness and identify blockers
Context: Migration Maturity
Immature: Ad hoc migrations, no planning, high risk of failure
Developing: Discovery done, basic wave plan, some testing
Managed: Dependency mapping, wave execution, validation, rollback plan → Target
Optimized: Automated discovery, real-time risk scoring, self-healing post-migration
Required Inputs
- Workload inventory: Applications, databases, storage, and external dependencies
- Current infrastructure: Hosting stack (VMware, Hyper-V, cloud competitors)
- Constraints: Downtime window, cutover blackout dates, compliance/data residency
- Success criteria: Performance targets, cost targets, SLA requirements
- Team: Who executes? Internal, partner, Microsoft FastTrack?
Decision Tree
What's the migration strategy for each workload?
├─ Rehost (lift-and-shift) → Move VM as-is, minimal changes
├─ Replatform (lift, tinker, shift) → Update OS/runtime, same app logic
├─ Refactor (re-architect) → Rebuild for cloud-native (containers, serverless)
├─ Replace (buy SaaS) → Decommission, switch to SaaS alternative
└─ Retain → Stay on-premises (not migrating)
What's the business criticality and complexity?
├─ Low complexity, non-critical → Migrate first (learn fast)
├─ Medium complexity, moderate criticality → Migrate mid-wave
└─ High complexity, critical → Migrate last (proven process)
How much downtime is acceptable?
├─ Zero downtime (active-active) → Requires dual-run, complex
├─ Few hours (typical) → Scheduled cutover window
├─ Days/weeks (acceptable) → Phased over time
└─ Unlimited (decommissioned) → Can take time
Are there compliance/data residency constraints?
├─ No → Full flexibility, optimize for cost/speed
├─ Yes → Choose Azure region carefully, plan audit trail
└─ Multi-region required → Plan for data synchronization
Workflow
Phase 1: Discovery & Assessment
- Collect inventory:
```bash
# Use Azure Migrate
az migrateprojects create --resource-group $RG \
--migrate-project-name "migration-prod" \
--location "eastus"
# Discover on-premises:
# ├─ VMs (Hyper-V, VMware, physical)
# ├─ Databases (SQL Server, Oracle, PostgreSQL)
# ├─ File shares and storage
# └─ Network and firewall rules
```
- Map dependencies:
```
Application Tiers:
Frontend (Web):
└─ asp-web-01 (4-core, 8GB)
└─ asp-web-02 (4-core, 8GB)
└─ Depends on: api-backend, load balancer
Backend (API):
└─ api-backend-01 (8-core, 16GB)
└─ api-backend-02 (8-core, 16GB)
└─ Depends on: sql-db, cache, message queue
Data:
└─ sql-db (2-core, 32GB, 500GB storage)
└─ cache (2-core, 4GB)
└─ msg-queue (shared, 100GB)
```
- Assess readiness:
```
Checklist:
✓ OS supported by Azure (Windows Server 2012+, Linux)
✓ No unsupported drivers/hardware
✓ Network connectivity (ExpressRoute or VPN gateway planned)
✓ Licensing (can migrate with Software Assurance)
✓ Backup & DR strategy documented
✗ Custom middleware (Oracle WebLogic) → May need workarounds
⚠️ Large database (500GB) → Plan staging environment
```
- Calculate costs:
```
On-premises annual cost:
├─ Hardware/lease: $50K
├─ Datacenter/power: $15K
├─ Licensing: $30K
└─ Staff: $60K
Total: $155K/year
Azure annual cost estimate:
├─ VMs (2x D4s_v3): $2,176/month
├─ SQL Database (S3): $380/month
├─ Storage (1TB): $100/month
├─ Data transfer (egress): $500/month
└─ Networking: $200/month
Total: ~$45K/year → 71% cost reduction
```
Phase 2: Plan Migration Waves
- Define waves (sequence by risk):
```
Wave 1 (Non-critical, simple) - Week 1-2
├─ Dev/Test environments
├─ Non-customer-facing apps
└─ Risk: Low | Duration: 1 day | Rollback: Easy
Wave 2 (Medium criticality) - Week 3-4
├─ Internal tools, ops systems
├─ Secondary workloads
└─ Risk: Medium | Duration: 2-4 hours | Rollback: 1 hour
Wave 3 (Critical, complex) - Week 5-6
├─ Customer-facing API
├─ Database tier
└─ Risk: High | Duration: 4 hours | Rollback: 4 hours
Wave 4 (Legacy, low urgency) - Month 2
├─ Deprecated systems, archive data
└─ Risk: Low | Duration: Flexible | Rollback: None (decommission)
```
- Define success criteria per wave:
```
Wave 1 Validation:
✓ All VMs boot and pass health checks
✓ Application logs show no errors
✓ Network connectivity confirmed
✓ Backups run successfully
→ If all pass: Proceed to Wave 2 (hold 1 day for monitoring)
→ If any fail: Rollback and investigate
Wave 3 Validation (critical):
✓ Database migrated and schemas match (byte-level comparison)
✓ Performance benchmarks met (p95 latency <200ms)
✓ Users can log in and perform core operations
✓ Alerts firing correctly
→ Monitor for 24 hours before declaring success
```
Phase 3: Prepare Azure Landing Zone
- Create landing zone:
```bash
# Hub VNet for shared services
az network vnet create \
--resource-group $RG \
--name "hub-vnet" \
--address-prefix "10.0.0.0/16" \
--location "eastus"
# Spoke VNet for migrated workloads
az network vnet create \
--resource-group $RG \
--name "spoke-prod-vnet" \
--address-prefix "10.1.0.0/16" \
--location "eastus"
# Peer hub to spoke
az network vnet peering create \
--resource-group $RG \
--vnet-name "hub-vnet" \
--name "hub-to-spoke" \
--remote-vnet "/subscriptions/$SUB/resourceGroups/$RG/providers/Microsoft.Network/virtualNetworks/spoke-prod-vnet" \
--allow-vnet-access --allow-forwarded-traffic
```
- Setup connectivity:
```bash
# ExpressRoute (dedicated connection, recommended for large migrations)
OR
# VPN Gateway (cheaper, adequate for <100 Mbps)
az network vpn-gateway create \
--resource-group $RG \
--name "vpn-gateway" \
--vnet "hub-vnet" \
--public-ip-address "vpn-public-ip"
```
- Configure identity:
```bash
# Azure AD Connect (sync on-premises AD with Entra ID)
# Enables seamless login for users post-migration
```
Phase 4: Execute Migration
- Test migration (dry-run):
```
For Wave 1 Dev VM:
├─ Create snapshot of on-premises VM
├─ Replicate to Azure via Azure Migrate
├─ Boot test VM (non-production)
├─ Verify OS, applications, connectivity
├─ Take snapshots for rollback
├─ Validate performance (CPU, memory, disk I/O)
└─ Document issues and blockers
```
- Production migration (Wave 1):
```
Timeline:
00:00 - Pre-cutover validation
├─ On-premises: All health checks pass
├─ Azure: Landing zone ready, connectivity confirmed
└─ Rollback: Test executed successfully
01:00 - Begin replication
├─ Disable on-premises VM
├─ Final delta sync to Azure (5-10 min)
├─ Boot Azure VM
└─ Verify applications online
01:20 - Update DNS/routing
├─ Route traffic to Azure VM
├─ Monitor error rate and latency
└─ Alert on-call if issues
02:00 - Validation
├─ Run smoke tests (login, core operations)
├─ Check logs for errors
├─ Verify backup job runs
└─ Declare success or rollback
```
- Handle database migrations (special care):
```
For SQL Server Database:
Option 1: Azure Database Migration Service (DMS)
├─ Continuous replication (minimal downtime)
├─ Schema sync automatically
└─ Cutover: Switch connection string
Option 2: Full backup/restore
├─ Backup from on-premises
├─ Upload to storage
├─ Restore to Azure SQL
└─ Run validation queries
Option 3: Native replication
├─ Setup Always-On Availability Group
├─ Sync on-premises to Azure
├─ Failover when ready
└─ Decommission on-premises replica
```
Phase 5: Validate & Optimize
- Post-migration validation:
```
Functional:
✓ All applications running (no errors in app logs)
✓ Users can access (login successful)
✓ Data integrity (row counts match, checksums pass)
✓ Integrations working (APIs, file shares accessible)
Performance:
✓ CPU utilization < 80%
✓ Memory utilization < 85%
✓ Disk I/O latency < 10ms
✓ Application response time: p95 < SLA
Operational:
✓ Backups running successfully
✓ Monitoring/alerting active
✓ Patch management configured
✓ Cost tracking shows expected usage
```
- Optimize sizing (reduce costs post-migration):
```
Day 1 (over-provisioned for safety):
├─ Web tier: 2x D4s_v3 (4-core, 16GB) = $240/month
├─ API tier: 2x D8s_v3 (8-core, 32GB) = $480/month
└─ Total: $720/month
Day 30 (after monitoring):
├─ Web tier: Actually uses 20% CPU, 40% memory
├─ Downsize to: 1x D2s_v3 (2-core, 8GB) = $60/month
├─ API tier: Actually uses 30% CPU, 50% memory
├─ Downsize to: 1x D4s_v3 (4-core, 16GB) = $120/month
└─ Savings: $540/month (75% reduction)
```
- Decommission on-premises:
```
After 30 days in production (stable):
├─ Keep on-premises running as backup (DR failback if needed)
├─ Reduce licensing/support cost
├─ Plan hardware decommissioning (6 months)
└─ Document lessons learned
```
Output Contract
- Migration Strategy
- Rehost/replatform/refactor approach per workload
- Dependency map and criticality ranking
- Readiness assessment (blockers, risks)
- Wave Plan
- Sequence (Wave 1, 2, 3...)
- Workloads per wave
- Timeline and blackout windows
- Success criteria and validation steps
- Risk Assessment
- Identified risks (data loss, downtime, performance)
- Mitigation strategies
- Rollback procedures
- Cutover Runbook
- Hour-by-hour timeline
- Pre-cutover validation checklist
- Go/no-go decision criteria
- Rollback triggers
- Post-Migration Plan
- Validation checklist (functional, performance, ops)
- Cost optimization (right-sizing)
- Decommissioning timeline (on-premises)
Guardrails
- Don't skip dependency mapping: Hidden dependencies cause cutover failures.
- Include rollback path: Every wave must have <4-hour rollback procedure.
- Validate before/after: Use checksums, row counts, smoke tests.
- Plan data sync carefully: Large databases need careful timing to avoid data loss.
- Communicate with users: Publish maintenance windows, expected downtime.
- Test in dev first: Execute exact same procedures in non-prod before production.
- Monitor obsessively post-cutover: First 24 hours are highest risk; watch logs/alerts closely.