Senior pm is an AI agent skill from the GitHub repository borghei/Claude-Skills. Scores portfolio health, risk exposure and resource capacity from a project JSON and frames board-ready status reports. Use when running a portfolio review, writing an executive RAG report, or rebalancing people across projects.

How to use this skill

Skill file

Senior Project Management Expert

Overview

Portfolio-level project management for enterprise software and SaaS: which projects need attention, where the risk sits, whether the people exist to deliver, and how to tell executives. The tools do the arithmetic deterministically; your job is to check their inputs, read the results against the context, and turn them into a decision someone can make.

Done looks like: every red or amber project is named with its weakest dimension and a recommended action; every top risk has an owner and a mitigation; capacity gaps are stated in hours per week with the people or dates that close them; the executive ask sits in the first 100 words.

When to Use

Single-team sprint health belongs to scrum-master/; cross-team dependency and milestone tracking to program-manager/.

Clarify First

Before generating the report or analysis, settle the inputs below. When one is missing or vague and would change the result, ask about it; when it wouldn't, use a sensible default and say which one you used.

Ask about the two or three inputs that matter most for this request, not the whole list. If the user wants a result straight away, produce it and state your assumptions at the top.

Quick Start

Run from the skill folder (project-management/senior-pm/). All four tools print text by default and JSON with --format json.

# Portfolio health: per-project timeline/budget/scope/quality/risk scores and RAG
python3 scripts/project_health_dashboard.py assets/sample_project_data.json

# Risk register: probability x impact matrix, categories, overdue mitigations
python3 scripts/risk_matrix_analyzer.py assets/sample_project_data.json --format json

# Capacity: utilisation per person, weekly demand vs capacity, gaps per project
python3 scripts/resource_capacity_planner.py assets/sample_project_data.json

# Stakeholders: Mendelow quadrant, communication plan, blocker strategies
python3 scripts/stakeholder_mapper.py assets/sample_stakeholders.json

assets/expected_output.json holds the key numbers these commands produce on the sample, so you can confirm a change did not break the maths.

Inputs and how the numbers are derived

sample_project_data.json is one portfolio file with portfolio_metadata, projects, resources and risks. The first three tools read it directly:

| Tool | Reads | Derived values |

|------|-------|----------------|

| project_health_dashboard.py | projects[], risks[] | Timeline: planned end plus days_behind_schedule. Budget: estimate at completion = spent / progress once 20% done, else spent + remaining. Scope: share of milestones due by the as-of date that are complete, less 0.03 per scope change. Quality: 0.7 x test pass rate + 0.3 x coverage, left out (weights renormalised) when both are 0. Risk: sum of probability x impact over the project's open risks. |

| risk_matrix_analyzer.py | risks[] | Score, level, category concentration, mitigations past target_resolution |

| resource_capacity_planner.py | resources[], projects[] | Weekly demand = remaining budget / blended hourly rate of assigned people, spread over the weeks left; allocation = each person's utilisation split across current_projects |

| stakeholder_mapper.py | stakeholders[] (see assets/sample_stakeholders.json) | Quadrant from power and interest (1-10, threshold 5) |

A flat per-project schema (project_id, planned_budget, forecasted_total_cost, ...) is also accepted; see the docstrings. These derivations are heuristics: say so when a number drives a decision, and override with real forecasts when the team has them.

Dates. Schedule, milestone and overdue checks use --as-of YYYY-MM-DD, defaulting to portfolio_metadata.generated_on and otherwise the latest date in the file, so a report is reproducible and the sample does not drift with today's date. Pass --as-of with today's date for a live review.

Exit codes. 0 report produced · 2 missing or unreadable file, invalid JSON, or the wrong shape (for example no projects, a project without id, no stakeholders). The tools report; they do not gate, so a red project still exits 0.

Anti-Patterns

Burying the ask in the executive report

Mistake: The 20-slide deck puts the decision the exec must make on slide 14.

Why it happens: Decks follow the order the work happened, so the ask lands at the end.

Instead: Put the decision or ask on slide 1 or in the first 100 words. Any ask past slide 5 means the report needs restructuring. Executives skim, and a missed ask leads to a decision made on incomplete data.

Averaging the portfolio into one color

Mistake: The dashboard shows portfolio health as a single R/Y/G. Two projects are red, but the aggregate reads yellow.

Why it happens: One summary color is what executives asked for, and averaging is the easy way to produce it.

Instead: Name each red project next to any aggregate from project_health_dashboard.py. Eight greens and two reds is not a yellow portfolio. It has two projects that need attention now.

A risk matrix with no mitigations

Mistake: The risk matrix plots 22 risks by probability and impact, with no mitigation column.

Why it happens: Plotting and scoring feel like the analysis, so the plan for each risk gets left for later.

Instead: Give every risk a mitigation before the matrix goes to anyone. risk_matrix_analyzer.py outputs a mitigation strategy, so carry it into the report instead of showing the plot alone.

Seven more, each with a bad and a good example: references/red-flags.md.

Reference Documentation

Load the reference that matches the task — keep this file lean and pull detail on demand:

Scope & Limitations

In Scope: Multi-project portfolio health assessment with weighted composite scoring; probability/impact risk analysis with category weighting (EMV and Monte Carlo by hand, guided by the references); resource capacity planning with utilization optimization and skill-matching; stakeholder mapping with Mendelow's Matrix and targeted communication plans; executive-level reporting with RAG status dashboards and strategic recommendations.

Out of Scope: Sprint-level team management (see scrum-master/); product backlog management and feature prioritization (see execution/prioritization-frameworks/); agile coaching and team maturity (see agile-coach/); financial modeling beyond project-level ROI (see finance/); contract negotiation and procurement.

Important Caveats: Health scores use fixed thresholds (see the script headers); calibrate them to your portfolio. The tools do not compute EMV or Monte Carlo forecasts; references/risk-management-framework.md explains how to do that by hand when the decision warrants it. Capacity is a weekly snapshot and assumes the named resources are the whole team, so a project staffed partly by people outside the file shows a large gap; check that before escalating. Inputs are self-reported and the tools check arithmetic, not truth.

Integration Points

| Integration | Direction | Description |

|------------|-----------|-------------|

| scrum-master/ | Receives from | Sprint velocity and health metrics feed portfolio-level health dashboards |

| sprint-retrospective/ | Receives from | Retro insights inform stakeholder reports and process improvement tracking |

| execution/brainstorm-okrs/ | Feeds into | Portfolio priorities and strategic context shape quarterly OKR themes |

| execution/outcome-roadmap/ | Feeds into | Portfolio health data influences roadmap commitment levels (Now/Next/Later) |

| discovery/pre-mortem/ | Receives from | Launch-blocking tigers escalate into portfolio risk register |

| execution/release-notes/ | Complements | Release notes incorporate stakeholder communication plans from mapper |

| Jira via Atlassian MCP | Bidirectional | Pull project data for health analysis; push status reports to Confluence |

| Financial Systems | Receives from | Real-time budget and spend data for variance analysis |

Files

| File | Purpose |

|------|---------|

| scripts/project_health_dashboard.py | Per-project health scores, RAG, interventions |

| scripts/risk_matrix_analyzer.py | Risk matrix, categories, overdue mitigations |

| scripts/resource_capacity_planner.py | Utilisation, demand vs capacity, gaps |

| scripts/stakeholder_mapper.py | Mendelow quadrants and communication plan |

| assets/sample_project_data.json | Four-project portfolio with resources and risks |

| assets/sample_stakeholders.json | Ten stakeholders for the mapper |

| assets/expected_output.json | Key results of the first three tools on the sample |

| assets/*_template.md | Charter, RACI, stakeholder map and executive report templates |