Launch playbook is an AI agent skill from the GitHub repository borghei/Claude-Skills. Coordinate a launch from T-30 to T+30: owners, run-of-show, internal and external comms, rollback and retro. Use when a feature goes GA after beta, a major release ships, or a product is relaunched.

How to use this skill

Skill file

Launch Playbook (Internal + External Coordination)

Overview

A complete launch coordination playbook for software products and features. It covers the three windows that matter -- pre-launch (T-30 to T-1), launch day (T-0), and post-launch (T+1 to T+30) -- and produces five concrete artifacts: a run-of-show, an internal comms plan, an external comms checklist, a rollback plan, and a post-launch retro template.

Most failed launches are not failed builds; they are failed coordination. Engineering ships on time, but support has not been trained, sales does not have collateral, the changelog is wrong, the rollback path was never tested, and the executive sponsor hears about a customer complaint before hearing about the launch. This playbook prevents those failures by assigning every owner and every artifact before T-30.

When to Use

When NOT to use: continuous-delivery bug fixes and minor improvements (use release-notes/ only); internal-only changes with no external comms (use a release runbook); product sunsets and deprecations (use eol-communication/).

Clarify First

Before building the launch plan, settle the inputs below. When one is missing or vague and would change the result, ask about it; when it wouldn't, use a sensible default and say which one you used.

Ask about the two or three inputs that matter most for this request, not the whole list. If the user wants a result straight away, produce it and state your assumptions at the top.

Workflow

The dates below are defaults for a GA launch with external comms [RECOMMENDED]. For a small or progressive launch, compress them (for example T-10 kickoff, sign-off at T-3, go/no-go at T-1) but keep the order: owners, then artifacts, then a tested rollback, then go/no-go.

  1. Kickoff at T-30. Confirm date, launch type and exec sponsor; open the run-of-show and internal comms plan.
  2. Assign owners within about 48 hours, every workstream named; unowned work is where launches fail.
  3. Build and sign off the five artifacts before T-7, and drill the rollback by T-7 so there is time to fix what the drill finds.
  4. Go/no-go at T-3, run launch day from one run-of-show, stabilise T+1 to T+7, run the 30-day retro.

Done when every artifact has a named owner and sign-off, the rollback was drilled, and the go/no-go decision is recorded with who made it.

Full timeline tables, RACI matrix, launch-type rules, and the 10-step workflow are in references/launch-timeline-and-execution.md.

Anti-Patterns

Launch message that doesn't match the rollout

Mistake: The launch post says "available to all customers today" while engineering ramps from 5% to 100% over a week. Most readers click through and hit "not available".

Why it happens: PMM and engineering each plan their own track, and nobody reads the two side by side.

Instead: At T-7, have PMM and the Eng Lead review the public messaging against the rollout plan together. Any mismatch in scope or timing gets fixed in the copy, for example "rolling out this week".

Launching on the calendar after a failed beta gate

Mistake: The beta exit memo shows the outcome gate missed (38% vs a 50% target), and the team launches anyway because the date was promised.

Why it happens: The date is public or committed upward, and "ship and iterate" sounds reasonable.

Instead: Re-read the beta exit memo before the go/no-go decision. Any failed gate gets addressed before T-0 or the date moves. Re-baseline the date with the exec sponsor. The criteria are the gate, the calendar is not.

Support not trained before launch

Mistake: Launch day brings a ticket spike, and agents answer "let me check on that" because the runbook is still a draft.

Why it happens: Support prep gets scheduled last, after the build and the external comms.

Instead: Finish the support runbook by T-14, run mandatory training at T-7, and pre-write macros for the top 10 expected questions. At T-3, ask 2 agents how to handle a likely ticket. If they hesitate, training is missing.

Nine more, each with a bad and a good example: references/red-flags.md.

Files

| File | Purpose |

|---|---|

| assets/launch-run-of-show.md | Hourly launch-day run-of-show |

| assets/internal-comms-plan.md | Internal comms before, during and after launch |

| assets/external-comms-checklist.md | Press, blog, email, enablement, support and legal checklist |

| assets/rollback-plan.md | Rollback decision matrix, drill checklist, runbook |

| assets/post-launch-retro.md | 7-day and 30-day retro |

| examples/shared-dashboards-ga-launch.md | Worked GA launch |

References

Scope & Limitations

In Scope: GA launch coordination across Engineering, Product, PMM, Sales, Support, Legal; run-of-show, rollback plan, comms plans, post-launch retrospective; big bang, progressive rollout, and dark launch patterns; T-30 to T+30 timeline; RACI assignment for cross-functional launches.

Out of Scope: Beta program execution (beta-program/); release notes content generation (release-notes/); end-of-life / sunset communication (eol-communication/); incident response runbooks (delivery-manager/ and engineering on-call); marketing campaign performance analysis beyond the 30-day window (handoff to demand gen).

Important Caveats: A launch is not a moment; it is a 60-day window (T-30 to T+30) -- staff accordingly. The single most common cause of failed launches is a missing RACI assignment, not a missing artifact: if you can name the artifact but not the owner, the artifact will not exist. Big-bang launches concentrate risk on one date; default to progressive rollout unless marketing leverage justifies the risk.

Integration Points

| Integration | Direction | What Flows |

|-------------|-----------|------------|

| beta-program/ | Receives from | Greenlit beta hands off testimonials, known issues, and pricing decision |

| create-prd/ | Receives from | PRD provides positioning, segments, and v1 scope |

| release-notes/ | Feeds into | Launch produces the GA release notes |

| daci-framework/ | Uses | Major launch decisions (go/no-go, rollback) use DACI |

| eol-communication/ | Complementary | Launches that replace older features trigger sunset comms |

| delivery-manager/ | Uses | Deployment, on-call rota, and rollback execution |

| senior-pm/ | Reports to | Exec sponsor receives T-1, T+1, T+7, T+30 updates |

| summarize-meeting/ | Feeds into | War-room standups and retro produce structured summaries |

| status-update-generator/ | Feeds into | Post-launch metrics roll up into weekly status |