Scoping

From Crapule421/tiger-team · View interactive version

Scoping is an AI agent skill from the GitHub repository Crapule421/tiger-team. Produce a scoping note (note de cadrage) - context, objectives, scope, stakeholders, constraints, plan, governance - plus a RACI, an initial RAID log and the experts to involve. Use at the start of an integration project or to re-scope one.

How to use this skill

Skill file

Task: scoping note (note de cadrage) + RACI + initial RAID

Input: $ARGUMENTS

You do not see the prior conversation: work only from the input above and the files it points to.

0. Intake

1. Confidentiality gate (mandatory, before any analysis)

Stop and ask the user for an anonymised version, without producing the deliverable, if the input contains any of:

Reply only with the category found (never the content) and what to redact. Generic system names, volumes and technologies are fine.

2. Load the knowledge

Read ${CLAUDE_PLUGIN_ROOT}/skills/pm-playbook/SKILL.md (sections 2-6, 14, 15, 17 are the core for scoping).

Read the templates if present and follow their structure: ${CLAUDE_PLUGIN_ROOT}/skills/deliverables/templates/raci.md and ${CLAUDE_PLUGIN_ROOT}/skills/deliverables/templates/raid.md. If a template is absent, use the formats below.

For regulatory applicability, rely on the sector-compliance skill and Read the matching sector reference when the sector applies: ${CLAUDE_PLUGIN_ROOT}/skills/sector-compliance/references/banking.md, healthcare.md or defense.md (same folder).

If the project involves a structural architecture choice or a sovereignty question, also skim ${CLAUDE_PLUGIN_ROOT}/skills/architecture-reference/SKILL.md (sections 4-6, 8) to state constraints correctly — do not make the architecture decision, list it as an open decision for the enterprise architect.

3. Analyse

  1. Identify the sector context (banking, healthcare, defense, public sector, industry, other) and derive the regulatory perimeter that plausibly applies (e.g., GDPR, DORA, NIS2, HDS, II 901 / IGI 1300, sector rules, public procurement). Mark each as "applies", "likely — confirm", or "to assess". Never assert a regulation applies without a stated reason; write "verify" when unsure of a detail.
  2. Build the integration inventory from the input: systems, flows (estimate count and complexity simple/medium/complex), protocols/formats, volumes, frequencies, latency needs, data owners, partners, environments, migration needs.
  3. Identify hard constraints: regulatory deadlines, change freezes, contract end dates, end-of-support dates, budget envelope.
  4. Identify long-lead items (flow openings, certificates, infra, licences, partner test slots, homologation, DPIA, CSE consultation).
  5. Estimate effort drivers and give a range (never a single figure), using the playbook heuristics; say which heuristics you applied.

4. Produce the deliverable (Markdown)

Scoping note (note de cadrage) — <project name or "Project X">

  1. Context and drivers — why, why now, cost of doing nothing.
  2. Objectives — measurable; and explicit non-objectives.
  3. Scope — table Item | IN / OUT | Comment covering processes, entities/sites, systems, flows, data domains, environments, migration.
  4. Stakeholders — table Stakeholder / role | Interest / concern | Influence (H/M/L) | Involvement.
  5. Constraints — regulatory (with applicability status), contractual, calendar, technical, budget, staffing.
  6. Integration inventory — table System | Role in project | Owner | Technology/platform | Flows in/out (est.) | Notes; then flow summary by complexity.
  7. High-level plan and milestones — phases with indicative durations, milestones (jalons), long-lead items, critical path drivers, freeze periods to avoid. Use a Markdown table; dates relative (M0, M+2…) unless the input gives dates.
  8. Budget / effort drivers — drivers, order-of-magnitude range with confidence (e.g., −30 % / +50 %), contingency recommendation.
  9. Governance — committees (COPIL, COPROJ, comité de suivi, design authority, CAB, security/homologation), cadence, members, decision rights, escalation tolerances.
  10. Acceptance approach — test levels foreseen (incl. UAT/recette, VABF/VSR if contractual), go/no-go principle, hypercare duration.
  11. Run target — who operates, support levels, service hours, DEX expectation.

RACI

Matrix of key activities (at least: scoping validation, functional specs, interface contracts, DAT, flow openings, test strategy, test data anonymisation, UAT, security risk acceptance/homologation, DPIA if personal data, DEX, cut-over plan, go/no-go, rollback decision, hypercare exit) × roles; use the role codes of raci.md (SPO, PM, BO, EA, SEC, DPO…) when the template is present. Exactly one A per row.

Initial RAID log

If raid.md is present, use its four tables and ID prefixes (Risks RSK-, Assumptions ASM-, Issues ISS-, Dependencies DEP-) and its scales; otherwise one table ID | Type (R/A/I/D) | Description | Probability (1-4) | Impact (1-4) | Criticality | Owner | Response / mitigation | Due date | Status. At least 8 risks relevant to the input (not generic filler), all assumptions you made, known dependencies with external parties.

Tiger Team experts to involve

Table Expert | Why (trigger found in the input) | When (phase) | First questions to address. Use only these agents: project-manager, enterprise-architect, devsecops-expert, security-expert, dba-expert, scheduling-expert, integration-expert, erp-expert, infra-expert, ibmi-expert. Include an expert only with a concrete trigger from the input; list explicitly those not needed and why (one line).

Decisions needed at COPIL #1

Numbered list of decisions/arbitrations with options and the recommended option.

Risks

Table Risk | Criticality (Critical/High/Medium/Low) | Mitigation — the top risks from the RAID log.

Handoffs

Only when there is a real point, one typed line per handoff: → <agent-name> | <claim: what you assert or need, one sentence> | <evidence: source, file:line, or "assumption"> | <needs: confirm / adjust / provide <what>>. Names: project-manager, enterprise-architect, devsecops-expert, security-expert, dba-expert, scheduling-expert, integration-expert, erp-expert, infra-expert, ibmi-expert. Example: → infra-expert | the CFT acknowledgment flow SRV-SAP-01 → SRV-BATCH-01 is missing from the flow matrix | interface contract §4 | provide the firewall rule and port. A settled point is not a handoff.

Open questions

Numbered, each with the person/role who can answer.

Assumptions

Numbered, each marked as validated by whom/when it must be confirmed.

5. Quality bar

Answer in the language used in the input.