Release plan is an AI agent skill from the GitHub repository Crapule421/tiger-team. Produce a production release plan (fiche MEP) - prerequisites, timed run sheet with owners, communication, go/no-go checkpoints, verification tests, rollback with triggers and point of no return, hypercare. Use before a go-live or cut-over.

How to use this skill

Skill file

Task: production release plan (fiche MEP) and cut-over run sheet

Input: $ARGUMENTS

You do not see the prior conversation: work only from the input above and the files it points to.

0. Intake

1. Confidentiality gate (mandatory, before any analysis)

Stop and ask the user for an anonymised version, without producing the plan, if the input contains any of:

Reply only with the category found (never the content) and what to redact.

2. Load the knowledge

3. Analyse

  1. Determine the release type: new system go-live, cut-over with data migration, interface/flow switch, version upgrade, infrastructure move; and the cut-over strategy (big bang, phased, parallel run, pilot, blue/green/canary). If not given, choose and justify it.
  2. List components and teams involved (applications, databases, middleware, scheduling plan, network/firewall, certificates, partners, ERP, IBM i…).
  3. Compute the timeline backwards from the business reopening deadline: forward path duration + verification + margin (≥ 20-30 % of the forward path) + rollback duration must fit inside the window before the point of no return. If it does not fit, say so explicitly as a Critical risk and propose options (phasing, pre-migration of history, longer window).
  4. Identify the point of no return (PNR): the step after which rollback is costlier/riskier than fix-forward (e.g., new transactions created in target, data sent to partners, source altered). Give its planned clock time.
  5. Define measurable rollback triggers (pre-agreed, no debate needed before PNR).

4. Produce the deliverable (Markdown)

Use the template's IDs throughout: REL- release, PRE-nn prerequisites, GNG-n checkpoints, run-sheet step numbers, RB-nn rollback steps, JOB-/FLW-/INT- for the objects touched.

Release sheet (fiche MEP) — <release name or "Release X">

  1. Identification — release ID (REL-YYYY-nnn), change/CAB reference (placeholder), version(s), perimeter, release type and strategy, window (start/end, business reopening deadline), cut-over manager role, decision makers.
  2. Scope and impacts — components changed; impacted users, entities, partners; service unavailability (what, how long); dependencies.
  3. Prerequisites — checklist table # | Prerequisite | Owner | Evidence | Due (D-x) | Status: UAT signed (PV de recette, reservations listed), non-regression and performance results, security findings closed or formally accepted, homologation decision if required, DEX validated by operations, monitoring/alerts configured, backups taken and restore tested, flows/firewall rules and certificates verified in production, scheduling plan changes prepared, packages built and checksums recorded, rollback rehearsed, dress rehearsal duration measured, partners confirmed, CAB approval, change freeze check, support and hypercare roster, communication messages pre-written.
  4. Run sheet (timed) — table # | Planned start | Duration | Planned end | Step | Owner (role) | Backup | Prerequisite step | Verification / evidence | Rollback step ref | Status. Use clock times relative to H0 (e.g., H0+00:30) unless real times are given. Group by phases: preparation (D-7 to D-1), freeze and backups, deployment, data migration and reconciliation, configuration and flow switch, scheduling activation, technical verification, business verification, opening. Insert explicit GO/NO-GO checkpoint rows and the PNR row.
  5. Go/no-go criteria and checkpoints — table Checkpoint | Time | Decision owner | Criteria (measurable) | Inputs: at least GNG-0 (D-5 readiness), GNG-1 (D-1 final go), GNG-2 (H0 start), GNG-3 (pre-PNR), GNG-4 (opening after verification). Decision options: Go / Conditional go (only for conditions achievable before PNR, with owner and deadline) / No-go.
  6. Verification tests — technical smoke tests (services up, connectivity, queues, file transfers, jobs, logs, monitoring green), functional/business verification scenarios with key users, data reconciliation (counts, control totals, samples, rejects), end-to-end flow tests with partners, first batch cycle checks. Table # | Test | Executed by | Expected result | Evidence | Blocking? (Y/N).
  7. Rollback plan — rollback strategy per component; triggers table Trigger | Threshold / measure | Detected by | Decision owner; rollback steps timed (same columns as run sheet) with duration; latest rollback start time to still reopen on time; PNR definition and time; after-PNR fix-forward and degraded-mode plan; data handling for transactions created during the window.
  8. Communication plan — table When | Audience | Message | Channel | Sender: pre-announcement, reminder, start, each checkpoint outcome, end of intervention / service reopened, incident or rollback notice, hypercare contacts. Name a single communication owner and a timestamped event log (main courante).
  9. Organisation during the window — roles (cut-over manager, technical leads per domain, DBA, ops, scheduling, network, security, vendor on-call, business verifiers), bridge/war-room details placeholder, escalation chain, contact list placeholders (roles only).
  10. Hypercare — duration (include at least one full business cycle, e.g., month-end), war room cadence, extended support hours, KPIs and thresholds, fast-track fix process, exit criteria, handover to run (DEX, known errors, support levels).

Risks

Table Risk | Criticality (Critical/High/Medium/Low) | Mitigation — specific to this release (window fit, data volume, partner readiness, rollback feasibility, key people, freeze collisions…).

Handoffs

Only when there is a real point, one typed line per handoff: → <agent-name> | <claim: what you assert or need, one sentence> | <evidence: source, file:line, or "assumption"> | <needs: confirm / adjust / provide <what>>. Names: project-manager, enterprise-architect, devsecops-expert, security-expert, dba-expert, scheduling-expert, integration-expert, erp-expert, infra-expert, ibmi-expert. Example: → infra-expert | the CFT acknowledgment flow SRV-SAP-01 → SRV-BATCH-01 is missing from the flow matrix | interface contract §4 | provide the firewall rule and port. A settled point is not a handoff.

Open questions

Numbered, each with the role who can answer and the deadline (D-x) by which it must be answered.

Assumptions

Numbered; flag those that, if wrong, change the timeline or the PNR.

5. Quality bar

Answer in the language used in the input.