Speculative pipeline

From hashgraph-online/awesome-codex-plugins · View interactive version

Speculative pipeline is an AI agent skill from the GitHub repository hashgraph-online/awesome-codex-plugins. A pipeline execution strategy where downstream stages start before upstream stages finish, using staggered timing with configurable delays. The leader begins first, and followers start after a delay, building from whatever partial output exists. Combined with convergence loops, early follower output

How to use this skill

Skill file

Speculative-pipeline Strategy

Run pipeline stages with staggered timing instead of sequentially. The leader starts first;

followers start after a configurable delay and build from whatever upstream output exists at

that point. Combined with convergence loops, followers self-correct as upstream artifacts

arrive and stabilize.

Core Principle

**Start downstream work early with partial upstream output. Convergence loops correct the

errors introduced by working from incomplete input.**

The insight is that waiting for perfect upstream output is wasteful. A follower working from

80% of the upstream artifacts will produce output that is ~60-70% correct on the first pass.

But with convergence loops running, the follower re-reads the upstream artifacts on each

iteration and corrects course. By the time the leader finishes, the follower is already

most of the way done.


The Pattern

Sequential (Traditional)

Stage 1: Specs     ████████████████████                          (5 hours)
Stage 2: Plans                         ████████████████          (4 hours)
Stage 3: Implement                                     ████████  (3 hours)
                   ─────────────────────────────────────────────
                   Total: 12 hours

Speculative-pipeline (Staggered)

Stage 1: Specs     ████████████████████                          (5 hours)
Stage 2: Plans            ████████████████                       (4 hours, started 1.5h after Stage 1)
Stage 3: Implement              ████████████                     (3 hours, started 3h after Stage 1)
                   ─────────────────────────────────────────────
                   Total: ~7 hours

Why It Works

  1. Stage 2 starts after a 1.5-hour offset. By then, Stage 1 has produced a meaningful set of partial specs.
  2. Stage 2 generates plans from whatever specs are available. Some plans will be built on incomplete information.
  3. Stage 1 keeps refining specs. When Stage 2 loops back for its next pass, it picks up

the newly completed specs and adjusts its plans accordingly.

  1. Stage 3 starts after a 3-hour offset. By then, both specs and plans exist in draft form.
  2. All stages self-correct through iteration. Each pass re-reads the latest upstream artifacts. Mistakes caused

by working from partial input are washed out on subsequent passes.

The key mechanism is convergence -- the iterative loop that re-reads inputs each pass. Without

convergence loops, speculative-pipeline would produce garbage. With them, early errors wash out over

iterations.


Example: 3-Stage Pipeline

Directory Structure

context/
├── specs/              # Stage 1 output: implementation-agnostic specs
├── plans/              # Stage 2 output: framework-specific plans
├── impl/               # Stage 3 output: implementation tracking
└── prompts/
    ├── 001-generate-specs.md       # Stage 1 prompt
    ├── 002-generate-plans.md       # Stage 2 prompt
    └── 003-implement.md            # Stage 3 prompt

Terminal Commands

Open three terminal windows (or use tmux panes):

# Terminal 1: Specs from reference materials (leader -- starts immediately)
{LOOP_TOOL} context/prompts/001-generate-specs.md -n 5 -t 2h

# Terminal 2: Plans from specs (follower -- starts after 1-hour delay)
{LOOP_TOOL} context/prompts/002-generate-plans.md -n 5 -t 2h -d 1h

# Terminal 3: Implementation from plans (follower -- starts after 2-hour delay)
{LOOP_TOOL} context/prompts/003-implement.md -n 10 -t 1h -d 2h

Parameter reference:

Replace {LOOP_TOOL} with your convergence loop runner (any script or tool that repeatedly

executes a prompt against the codebase, committing between iterations).

What Happens Chronologically

| Time | Stage 1 (Specs) | Stage 2 (Plans) | Stage 3 (Implement) |

|------|-----------------|-----------------|---------------------|

| 0:00 | Starts. Reads refs, begins generating specs. | Waiting (1.5h delay). | Waiting (3h delay). |

| 1:30 | Iteration 1 complete. ~50% of specs written. Committed. | Starts. Reads partial specs, begins generating plans. | Waiting. |

| 3:00 | Iteration 2. Specs ~80% complete. | Iteration 1 complete. Plans based on partial specs. Some plans will need correction. | Starts. Reads partial specs + plans, begins implementing. |

| 4:00 | Iteration 3. Specs ~92% complete, converging. | Iteration 2. Re-reads updated specs. Corrects plans. Plans ~65% correct. | Iteration 1 complete. Some implementation based on incomplete plans. |

| 5:00 | Converged. Specs complete. Done. | Iteration 3. Re-reads final specs. Plans ~88% correct. | Iteration 2. Re-reads corrected plans. Fixes implementation. |

| 5:30 | -- | Iteration 4. Plans converged. Done. | Iteration 3. Implementation ~75% correct. |

| 7:00 | -- | -- | Iteration 4-5. Implementation converges. Done. |

Result: ~7 hours total versus ~12 hours sequential.


Choosing Delay Values

The delay determines how much upstream work exists when the follower starts. Too short and the

follower wastes iterations on garbage input. Too long and you lose the time savings.

Guidelines

| Upstream Stage Duration | Recommended Delay | Rationale |

|------------------------|-------------------|-----------|

| 1-2 hours | 15-30 minutes | Short stages produce useful partial output quickly |

| 2-4 hours | 1 hour | Enough time for the first iteration to complete and commit |

| 4+ hours | 1-2 hours | First iteration should have substantial output |

Rules of Thumb

  1. Delay >= 1 upstream iteration. The follower should not start until the leader has completed

at least one full iteration and committed results.

  1. Delay < 50% of upstream duration. If the delay is longer than half the upstream time, the

time savings are marginal.

  1. More follower iterations compensate for shorter delays. If you start the follower early

(aggressive delay), give it more iterations to converge.


Multi-Stage Pipelines (4+ Stages)

For pipelines with more than 3 stages, stagger each stage relative to Stage 1:

# 5-stage pipeline example
{LOOP_TOOL} {PROMPT_001} -n 5 -t 2h           # Stage 1: starts immediately
{LOOP_TOOL} {PROMPT_002} -n 5 -t 2h -d 1h     # Stage 2: 1h delay
{LOOP_TOOL} {PROMPT_003} -n 8 -t 1h -d 2h     # Stage 3: 2h delay
{LOOP_TOOL} {PROMPT_004} -n 8 -t 1h -d 3h     # Stage 4: 3h delay
{LOOP_TOOL} {PROMPT_005} -n 10 -t 45m -d 4h   # Stage 5: 4h delay

Notice the pattern:


When Speculative-pipeline Works Best

Good Fit

Poor Fit

complete output (e.g., code generation that requires a fully resolved type system), the

follower will produce only errors

worth the small time savings


Monitoring Speculative-pipeline Execution

What to Watch

  1. Follower diff sizes per iteration. If the follower's diffs are large on every iteration

(not decreasing), it is thrashing -- the delay was too short or the upstream output is

too unstable.

  1. Follower convergence rate. The follower should converge within 1-2 iterations of the

leader finishing. If it takes many more, the stages may have a hard dependency.

  1. Git commit frequency. Both leader and follower should be committing regularly. If commits

stall, the agent may be stuck.

Convergence Signals

A speculative-pipeline pipeline has converged when:

Thrashing Detection

Thrashing = the follower keeps making large changes because upstream output keeps changing.

Signs of thrashing:

Fix thrashing by:

  1. Increasing the delay (give the leader more time to stabilize)
  2. Reducing follower iterations (let upstream settle first)
  3. Adding a "wait for upstream convergence" gate between stages

Combining with Agent Teams

In multi-agent setups, speculative-pipeline applies at the pipeline level, not the agent team level:

Pipeline Level (speculative-pipeline timing):
  Stage 1 (Specs)     → Single agent or agent team
  Stage 2 (Plans)     → Single agent or agent team (starts after delay)
  Stage 3 (Implement) → Agent team dispatched via Agent tool (starts after delay)

Each stage can internally use agent teams (multiple teammates working in parallel on different

domains), but the stages themselves are staggered using speculative-pipeline timing.

Do not confuse:

They are orthogonal and composable.


Implementation Checklist

When setting up a speculative-pipeline pipeline: