Timeline generator

From autonomous-ai/autonomous-intern · View interactive version

Timeline generator is an AI agent skill from the GitHub repository autonomous-ai/autonomous-intern. Generates project timelines with phases, milestones, dependencies, critical path analysis, and Gantt-style visualizations. Use when the user says "create a project timeline", "estimate delivery dates", "build a roadmap", "identify the critical path", "adjust the schedule", "when will this be done",

How to use this skill

Skill file

Timeline Generator

Quick Start

Build project timelines by sequencing tasks and phases with dependencies, calculating the critical path, and adding 20% buffers at each phase level. Show both buffered and unbuffered end dates. Identify resource bottlenecks and parallel work streams.

Workflow

  1. Determine context: new full timeline, adjustment to existing schedule, or delivery date estimation
  2. Gather inputs: tasks/phases, effort estimates, team size, skill requirements, constraints
  3. Identify dependencies between tasks (finish-to-start by default)
  4. Note fixed dates: hard deadlines, external milestones, blackout periods
  5. Load existing project data and historical velocity if available
  6. Calculate start/end dates respecting dependencies and resource availability
  7. Add 20% buffer at each phase level
  8. Calculate critical path (longest dependent chain = minimum project duration)
  9. Set milestones at key checkpoints tied to measurable deliverables
  10. Detect resource bottlenecks and flag single points of failure
  11. Generate Gantt-style timeline with supporting detail tables

Examples

Example 1: New project timeline

Input: "Create a timeline for our mobile app MVP. Phases: Design (5 days), Backend API (10 days), Frontend (8 days, needs design done), Testing (5 days, needs backend and frontend), Launch (2 days). Team: 2 devs, 1 designer. Start March 18."

Output:

Project Timeline - Mobile App MVP
Duration: 18/03/2026 -> 06/05/2026 (7 weeks including buffers)
Unbuffered Duration: 18/03/2026 -> 28/04/2026 (6 weeks)
Team Size: 3 people

Milestones:
| # | Milestone | Deliverable | Target Date | Dependencies |
|---|-----------|------------|-------------|-------------|
| M1 | Design Complete | Approved mockups & specs | 25/03/2026 | - |
| M2 | API Ready | All endpoints deployed to staging | 11/04/2026 | - |
| M3 | Feature Complete | Frontend integrated with API | 22/04/2026 | M1, M2 |
| M4 | QA Passed | All test cases passing | 30/04/2026 | M3 |
| M5 | Launch | App live in store | 06/05/2026 | M4 |

Timeline (Gantt View):
Week 1      |======          | Design (5d + 1d buffer)
Week 1-3    |  ============  | Backend API (10d + 2d buffer) [parallel]
Week 2-4    |    ==========  | Frontend (8d + 2d buffer) <- Design
Week 4-5    |          ======| Testing (5d + 1d buffer) <- Backend + Frontend
Week 6      |            ====| Launch (2d + 1d buffer) <- Testing
             M1    M2   M3  M4  M5

Critical Path:
Design -> Frontend -> Testing -> Launch
Critical Path Duration: 20 days unbuffered (4 weeks)

Phase Details:
| Phase | Effort | Buffer | Total | Start | End | Resources | Dependencies |
|-------|--------|--------|-------|-------|-----|-----------|-------------|
| Design | 5d | 1d | 6d | 18/03 | 25/03 | Designer | - |
| Backend API | 10d | 2d | 12d | 18/03 | 03/04 | Dev 1 | - |
| Frontend | 8d | 2d | 10d | 26/03 | 08/04 | Dev 2 | Design |
| Testing | 5d | 1d | 6d | 09/04 | 16/04 | Dev 1 + Dev 2 | Backend, Frontend |
| Launch | 2d | 1d | 3d | 17/04 | 21/04 | All | Testing |

Resource Allocation:
| Resource | Design | Backend | Frontend | Testing | Launch | Utilization |
|----------|--------|---------|----------|---------|--------|-------------|
| Designer | Lead | - | Support | - | - | 40% |
| Dev 1 | - | Lead | - | Lead | Support | 85% |
| Dev 2 | - | - | Lead | Support | Support | 70% |

Risks to Timeline:
- Designer is single point of failure for Design phase; any absence delays Frontend and critical path
- Backend and Frontend converge at Testing; delay in either pushes launch date

Example 2: Deadline feasibility check

Input: "Can we deliver the payment feature by April 1? Tasks: API design (3d), implementation (8d), testing (4d), all sequential. One developer."

Output:

Project Timeline - Payment Feature
Requested Deadline: 01/04/2026
Start Date: 18/03/2026

Phase Details:
| Phase | Effort | Buffer | Total | Start | End |
|-------|--------|--------|-------|-------|-----|
| API Design | 3d | 1d | 4d | 18/03 | 23/03 |
| Implementation | 8d | 2d | 10d | 24/03 | 04/04 |
| Testing | 4d | 1d | 5d | 07/04 | 11/04 |

Unbuffered End Date: 04/04/2026 (3 days late)
Buffered End Date: 11/04/2026 (10 days late)

DEADLINE NOT FEASIBLE

Critical Path: API Design -> Implementation -> Testing (all sequential, 15 days unbuffered)

Options to meet April 1 deadline:
1. Add a second developer: parallelize implementation to save ~4 days
2. Reduce scope: cut testing to 2 days (higher risk)
3. Start earlier: begin API design by March 13 to fit buffered schedule
4. Extend deadline: request April 11 to include full buffers

Tools

Error Handling

Connectors (Optional)

This skill works standalone. When connected to external tools, it unlocks additional capabilities:

| Connector | What it enables |

|-----------|----------------|

| ~~project tracker | Pull task data, dependencies, and completion status for timeline accuracy |

| ~~calendar | Check team availability and block milestone dates |

| ~~CI/CD | Link release milestones to deployment schedules |

| ~~docs | Access project plans, requirements, and scope documents |

Rules

Output Template

Project Timeline - [Project Name]
Duration: [Start Date] -> [End Date (buffered)] ([N weeks] including buffers)
Unbuffered Duration: [Start Date] -> [End Date (unbuffered)] ([N weeks])
Team Size: [N people]

Milestones:
| # | Milestone | Deliverable | Target Date | Dependencies |
|---|-----------|------------|-------------|-------------|
| M1 | [Milestone name] | [Specific deliverable] | [Date] | [Prerequisites] |

Timeline (Gantt View):
Week 1-2   |========        | Phase 1: [Name] (Est: [N]d + Buffer: [N]d)
Week 3     |    ====        | Phase 2: [Name] <- depends on Phase 1
Week 3-4   |      ========  | Phase 3: [Name] (parallel with Phase 2)
Week 5     |        ========| Phase 4: [Name] <- depends on Phase 2 & 3
            M1         M2   M3

Critical Path:
[Phase X] -> [Phase Y] -> [Phase Z]
Critical Path Duration: [N weeks] (unbuffered)

Phase Details:
| Phase | Effort | Buffer | Total | Start | End | Resources | Dependencies |
|-------|--------|--------|-------|-------|-----|-----------|-------------|
| [Name] | [N days] | [N days] | [N days] | [Date] | [Date] | [Names] | [Phase #] |

Resource Allocation:
| Resource | Phase 1 | Phase 2 | Phase 3 | Phase 4 | Utilization |
|----------|---------|---------|---------|---------|-------------|
| [Name] | [Role] | - | [Role] | [Role] | [%] |

Risks to Timeline:
- [Risk description and potential impact on delivery date]