Neqsim field economics

From equinor/neqsim · View interactive version

Neqsim field economics is an AI agent skill from the GitHub repository equinor/neqsim. Oil & gas field economics, NPV, IRR, cash flow, and fiscal regime modeling with NeqSim. USE WHEN: calculating project economics (NPV, IRR, payback), evaluating tax regimes (Norwegian NCS, UK, generic), building cost estimates (CAPEX/OPEX), or running Monte Carlo sensitivity analysis on economic outc

How to use this skill

Skill file

NeqSim Field Economics Skill

Reference for petroleum project economics — cost estimation, cash flow modeling,

tax regimes, NPV/IRR calculations, breakeven analysis, and uncertainty.


Economics Workflow Overview

Reservoir Volumetrics → Production Profile → Revenue Forecast
                                                    ↓
CAPEX Estimate → Cash Flow Engine ← OPEX Estimate
                       ↓
              Tax Model (NCS/UK/Generic)
                       ↓
              NPV / IRR / Payback / Breakeven
                       ↓
              Monte Carlo Uncertainty (P10/P50/P90)

Cost Estimation

CAPEX Components (Typical Offshore NCS)

| Category | Typical Range | NeqSim Class |

|----------|--------------|--------------|

| Wells (drilling + completion) | 200-800 MNOK/well | WellCostEstimator, WellMechanicalDesign |

| SURF (subsea, umbilicals, risers, flowlines) | 500-5000 MNOK | SURFCostEstimator |

| Topsides / Processing | 2000-15000 MNOK | FacilityBuilder + MechanicalDesign |

| Subsea equipment (trees, manifolds) | 100-500 MNOK/well | SubseaProductionSystem |

| Pipeline / Export | 50-300 MNOK/km | PipelineMechanicalDesign |

| FPSO hull + mooring | 5000-20000 MNOK | Parametric estimate |

| Decommissioning (ABEX) | 10-30% of CAPEX | DecommissioningEstimator |

NeqSim Cost Estimation Classes

// Well cost
WellCostEstimator wellCost = new WellCostEstimator();
wellCost.setRegion(SubseaCostEstimator.Region.NORWAY);
wellCost.setWaterDepth(350.0);
wellCost.setTotalDepth(3800.0);
wellCost.setDrillingDays(45);
wellCost.setCompletionDays(25);
wellCost.setRigDayRate(540000.0);  // USD/day
double wellCapex = wellCost.estimate();

// SURF cost
SURFCostEstimator surfCost = new SURFCostEstimator();
surfCost.setRegion(SubseaCostEstimator.Region.NORWAY);
surfCost.setNumberOfWells(4);
surfCost.setFlowlineLength(25.0);      // km
surfCost.setUmbilicalLength(27.0);     // km
surfCost.setWaterDepth(350.0);
surfCost.setTreeType("vertical");
surfCost.setHasManifold(true);
double surfCapex = surfCost.estimate();

// Regional cost factors
RegionalCostFactors factors = new RegionalCostFactors("Norway");
double adjustedCost = baseCost * factors.getCostMultiplier();

OPEX Components

| Category | Typical Range | Estimation Basis |

|----------|--------------|-----------------|

| Fixed OPEX | 3-6% of CAPEX/year | Insurance, manning, maintenance |

| Variable OPEX | 2-8 USD/boe | Chemicals, power, logistics |

| Well intervention | 50-200 MNOK/event | Frequency-based estimate |

| Pipeline inspection | 10-50 MNOK/year | IMR schedule |


Cash Flow Engine

Direct Lifecycle Integration

FieldLifecycleSimulator aggregates live NeqSim reservoir/process results by calendar year and feeds oil and export

gas volumes directly to CashFlowEngine("NO"). FieldLifecycleResult exposes after-tax NPV, IRR, payback and

break-even oil/gas prices together with the technical production, injection, energy and emissions profiles. Use this

route when economics must reflect process capacity and reservoir response rather than an independent decline curve.

For a host tieback, only the new field's attributed oil and gas enter project revenue; existing-host production is a

capacity load, not project revenue. Configure tieback tariff/OPEX and modification CAPEX explicitly. The result's

holdback, capacity-deferred oil, peak operating/requested utilization and annual bottleneck fields explain the economic

difference between standalone greenfield, direct tieback through existing SURF, managed allocation and debottleneck

cases. A user-supplied ProcessModel keeps the economic result coupled to all SURF and host process areas.

For area studies, use AreaDevelopmentEvaluator to compare multiple producing hosts and greenfield routes on the same

economic basis. A REJECT_OPTION product-quality policy makes an off-spec route ineligible before NPV ranking;

REPORT_ONLY preserves the route for sensitivity and debottleneck diagnosis.

Basic Usage

CashFlowEngine engine = new CashFlowEngine("NO");  // Norwegian tax regime
engine.setCapex(5000.0, 2025);       // MUSD, year
engine.setOpexPercentOfCapex(0.04);  // 4% of CAPEX/year
engine.setOilPrice(70.0);           // USD/bbl
engine.setGasPrice(0.30);           // USD/Sm3

// Add production year by year
for (int year = 2027; year <= 2045; year++) {
    engine.addAnnualProduction(year, oilSm3[year], gasSm3[year], waterSm3[year]);
}

CashFlowResult result = engine.calculate(0.08);  // 8% discount rate

double npv = result.getNpv();           // MUSD
double irr = result.getIrr();           // fraction (e.g., 0.15 = 15%)
double payback = result.getPaybackYears();
double pi = result.getProfitabilityIndex();

DCF Calculator (Low-Level)

DCFCalculator dcf = new DCFCalculator();
dcf.setDiscountRate(0.08);
double[] cashFlows = {-500, -300, 100, 200, 300, 250, 200, 150, 100};
double npv = dcf.calculateNPV(cashFlows);
double irr = dcf.calculateIRR(cashFlows);

Tax Models

Norwegian Continental Shelf (NCS)

The Norwegian petroleum tax regime has three key components:

| Component | Rate | Base |

|-----------|------|------|

| Corporate tax | 22% | Revenue - OPEX - Depreciation |

| Special petroleum tax | 56% | Revenue - OPEX - Depreciation - Uplift |

| Total marginal rate | 78% | — |

Additional features:

NorwegianTaxModel taxModel = new NorwegianTaxModel();
// Automatically applied when CashFlowEngine("NO") is used

// Direct tax calculation
TaxResult tax = taxModel.calculateTax(
    grossRevenue,    // NOK
    opex,            // NOK
    depreciation,    // NOK
    uplift           // NOK
);
double corporateTax = tax.getCorporateTax();
double specialTax = tax.getSpecialTax();
double totalTax = tax.getTotalTax();
double effectiveRate = tax.getEffectiveRate();

Regime gotcha (verified in task 2026-10-09 Havis screening): the registry "NO" model is the

pre-2022 uplift regime (6-year depreciation, uplift, loss carry-forward). Projects approved under

the current 2022 cash-flow tax (78 % on net cash flow, immediate expensing, immediate loss refund,

so after-tax cash flow = 22 % of pre-tax) must use

new GenericTaxModel(FiscalParameters.norwegianCashFlowTax2022()) (lossRefund(true), IMMEDIATE

depreciation). CashFlowEngine discounts at year end; state the convention (mid-year raises NPV by

about half a year of discounting) or discount outside the engine.

UK Continental Shelf (UKCS)

| Component | Rate | Notes |

|-----------|------|-------|

| Ring Fence Corporation Tax (RFCT) | 30% | Ring-fenced profits |

| Supplementary Charge (SC) | 10% | On ring-fenced profits |

| Total marginal rate | 40% | Investment allowance applies |

Generic Tax Model

GenericTaxModel generic = new GenericTaxModel();
generic.setCorporateTaxRate(0.25);
generic.setRoyaltyRate(0.10);
generic.setDepreciationYears(10);

Tax Model Registry

// List available models
TaxModelRegistry.getAvailableModels();  // ["NO", "UK", "BR", "GENERIC"]

// Get model by country code
TaxModel model = TaxModelRegistry.getModel("NO");

Brazil Special Participation (Participação Especial, Decreto 2.705/1998 Art. 22)

The registry's BR-DW model approximates SP as a flat 25 % resource tax. That

is a screening proxy only: the statutory SP is progressive in the quarterly

fiscalised volume (VPF, thousand m3 oil equivalent), with rates 10/20/30/35/40 %,

exemption volumes and deductions that depend on location (onshore / shallow /

deep water, >400 m) and production year (1, 2, 3, 4+). Use

BrazilSpecialParticipation for the statutory charge:

BrazilSpecialParticipation.Location loc =
    BrazilSpecialParticipation.Location.fromWaterDepth(2420.0);   // DEEP_WATER
double vpf = BrazilSpecialParticipation.toThousandM3OilEquivalent(oilSm3, gasSm3, 1000.0);
double eff = BrazilSpecialParticipation.getEffectiveRate(loc, 4, vpf); // share of RLP
double[] spPerYear = BrazilSpecialParticipation.calculateAnnualFromEqualQuarters(
    loc, annualNetRevenueRlp, annualVolumeThousandM3oe);          // year index 0 = first oil
double[] spPerQuarter = BrazilSpecialParticipation.calculateQuarters(
    loc, productionYearOfEachQuarter, quarterlyRlp, quarterlyVpf); // with Art. 22 §6 loss carry-forward

(Art. 25). Reinjected gas is not fiscalised; leave it out of VPF.

plateau (~2 100 thousand m3 oe/quarter) is in the 35 % band but pays ~18 % of RLP —

a flat 20–25 % proxy overstates SP for mid-size fields and understates it for giants.

continuity of the table requires 725; the class keeps the published value

(documented in JavaDoc) — confirm with ANP for shallow-water cases.

concession contracts.


Production Profile Generator

ProductionProfileGenerator gen = new ProductionProfileGenerator();
gen.setResourceVolume(100.0);    // MMboe
gen.setRecoveryFactor(0.55);
gen.setPeakRate(25000.0);        // boe/d
gen.setBuildUpYears(2);
gen.setPlateauYears(5);
gen.setDeclineType("exponential");
gen.setDeclineRate(0.12);        // 12%/year
gen.setProjectLife(25);          // years

double[] profile = gen.generate();  // Annual production (boe)

Sensitivity & Uncertainty Analysis

Tornado Diagram (One-at-a-Time)

SensitivityAnalyzer sensitivity = new SensitivityAnalyzer(engine);
sensitivity.addParameter("oilPrice", 50.0, 70.0, 90.0);     // low, base, high
sensitivity.addParameter("capex", 4000.0, 5000.0, 7000.0);
sensitivity.addParameter("recoveryFactor", 0.45, 0.55, 0.65);
sensitivity.addParameter("opexRate", 0.03, 0.04, 0.06);

Map<String, double[]> tornado = sensitivity.runTornado();
// Returns: {"oilPrice": [npv_low, npv_base, npv_high], ...}

Monte Carlo

MonteCarloRunner mc = new MonteCarloRunner(engine);
mc.addTriangularInput("oilPrice", 50.0, 70.0, 90.0);
mc.addTriangularInput("capex", 4000.0, 5000.0, 7000.0);
mc.addTriangularInput("recoveryFactor", 0.45, 0.55, 0.65);

MonteCarloResult result = mc.run(1000);
double p10 = result.getPercentile(10);
double p50 = result.getPercentile(50);
double p90 = result.getPercentile(90);
double probNegative = result.getProbabilityBelow(0.0);

Breakeven Analysis

// Breakeven oil price (NPV = 0)
double breakevenPrice = engine.calculateBreakevenPrice(0.0);

// Breakeven at different discount rates
for (double rate : new double[]{0.05, 0.08, 0.10, 0.12}) {
    double be = engine.calculateBreakevenPrice(rate);
    System.out.println("Breakeven at " + (rate*100) + "%: " + be + " USD/bbl");
}

Exploration commitment and relinquishment (EMV, break-even Pg)

A licence decision (keep and drill, or relinquish) is an option valuation, not a project NPV. With the NCS cash-flow tax (tau = 0.78, dry well refunded when a tax position exists):

EMV = Pg * V_dev - (1 - tau) * C_expl          (V_dev = expected post-tax development value if discovered, > 0 only)
Pg* = (1 - tau) C_expl / (V_dev + (1 - tau) C_expl)   (break-even chance of success)

Appraisal-first versus go-now strategies and design-to-cost (Ragnfrid Sor VPbo pattern).


Decommissioning Cost Estimation

DecommissioningEstimator decom = new DecommissioningEstimator();
decom.setNumberOfWells(6);
decom.setWellAbandonment(true);
decom.setSubseaRemoval(true);
decom.setPlatformRemoval(false);    // tieback — no platform
decom.setPipelineDecommissioning(true);
decom.setWaterDepth(350.0);
decom.setRegion("Norway");

double decomCost = decom.estimate();  // MUSD

Common Economic Pitfalls

| Pitfall | Impact | Prevention |

|---------|--------|------------|

| Double-counting depreciation in tax bases | Overstates tax, understates NPV | Norwegian model: depreciation deducted from BOTH bases independently |

| Wrong CAPEX timing | Wrong NPV (time value) | CAPEX in year 0, first production year 2-3, match reality |

| Ignoring loss carry-forward | Understates early-year cash flow | Norwegian model carries losses with interest adjustment |

| Using nominal discount rate with real cash flows | Wrong NPV | Be consistent: real-real or nominal-nominal |

| Ignoring decommissioning | Missing 10-30% lifecycle cost | Always include ABEX in project economics |

| Oil price in wrong currency | Wrong revenue | NOK on NCS, USD internationally; use consistent FX |

| runFieldEconomics/FiscalRegime NO is the pre-2022 uplift model | A post-2022 NCS project (22 % ordinary, 56 % special tax on cash flow, immediate expensing, refunded losses) gave NPV 0.09 vs 6.3 MUSD in a cross-check (NIP-1, BRP South Breidablikk) | For post-2022 NCS incremental projects build the annual cash flow yourself (7 % real, 6-year straight-line ordinary depreciation, special tax on cash flow) and use NeqSim only as a cross-check; state the regime used |


Key Conversion Factors

| From | To | Factor |

|------|-----|--------|

| 1 Sm3 oil | boe | 1.0 (by definition) |

| 1 Sm3 gas | boe | ~0.001 (varies, typically 1000 Sm3 gas = 1 boe) |

| 1 bbl oil | Sm3 oil | 0.159 |

| 1 Sm3 oil | bbl | 6.29 |

| 1 tonne oil | bbl | ~7.33 (depends on API gravity) |

| 1 BCF gas | Sm3 | 28.3 × 10⁶ |