Neqsim equipment cost estimation

From equinor/neqsim · View interactive version

Neqsim equipment cost estimation is an AI agent skill from the GitHub repository equinor/neqsim. Equipment and process CAPEX estimation - Turton/Peters/Seider correlations, CEPCI escalation, material/pressure factors, bare-module to grass-roots, AACE class 1-5, location and currency factors, mechanical-design-driven topsides/SURF/well rollups. USE WHEN: a task needs a Class 3/4 estimate for equ

How to use this skill

Skill file

NeqSim Equipment Cost Estimation Skill

Class-3/4 (AACE 18R-97) order-of-magnitude to study estimates for individual

process equipment and early process/facility CAPEX rollups - the bridge between

sized equipment and a project economics model. Wraps Turton (5e),

Peters–Timmerhaus, Ulrich, and Seider correlations with CEPCI escalation,

material factors, pressure factors, and Lang/Hand factors.

The preferred NeqSim path is mechanical-design driven: call each unit's

initMechanicalDesign(), calcDesign(), then

getMechanicalDesign().getCostEstimate().calculateCostEstimate() or let

ProcessCostEstimate.calculateAllCosts() do that rollup for a full flowsheet.

When to Use

For project-level economics, asset valuation, or fiscal regimes, use

CODE0. This skill is

the CAPEX basis skill that feeds those economics workflows.

AACE Cost Estimate Classes

| Class | Maturity | Accuracy | Method |

| ----- | ------------- | ------------- | ----------------------------- |

| 5 | Concept | −50% / +100% | Capacity-factor (six-tenths) |

| 4 | Pre-FEED | −30% / +50% | Equipment-factored (this skill) |

| 3 | FEED | −20% / +30% | Sized equipment + bulk MTOs |

| 2 | Detailed | −15% / +20% | Detailed quantity takeoff |

| 1 | Final | −10% / +15% | Vendor quotes |

Correlation Validity Range (READ THIS FIRST)

The Turton correlations are fitted over a stated capacity range. NeqSim does not refuse a

capacity outside that range — it evaluates the polynomial anyway and returns a number that looks

ordinary.

Observed case: a 239 MW compression duty evaluated against a correlation valid to 3000 kW

returned about 6 MUSD — roughly 80× too low, with no warning. In the same study the

weight-based calcColumnShellCost returned ~500 MUSD for a single contactor because it feeds a

shell weight into coefficients fitted on volume. The two errors partly cancelled, and the

study total was wrong by a factor of three while appearing internally consistent.

Rules:

  1. Check the range before calling. Compressors 450–3000 kW; pumps 1–300 kW; vessels by volume.
  2. Oversized duties are parallel units, not extrapolation. Split the duty into

ceil(capacity / max_capacity) units at capacity / n each and cost each inside the range.

CostEstimationCalculator now does this internally for compressors and pumps.

  1. Never use the weight-based vessel/column methods. calcVerticalVesselCost,

calcHorizontalVesselCost and calcColumnShellCost are deprecated: their capacity basis is

volume, not shell weight. Use calcVerticalVesselCostByVolume and pass the actual volume.

  1. Anchor the total. Cross-check specific CAPEX against a published comparable for the concept

type before believing the sum. A result outside the expected band by more than a factor of 1.5

is a bug until proven otherwise.

Pattern 1 — Bare-module Cost for a Vessel

import neqsim.process.costestimation.CostEstimationCalculator;

CostEstimationCalculator cost = new CostEstimationCalculator();
cost.setCurrentCepci(CostEstimationCalculator.CEPCI_2025);   // 840
cost.setMaterialOfConstruction("SS316");                     // sets Fm = 2.1
cost.setLocationByRegion("Norway");                          // location factor

double shellWeight_kg = 8500.0;        // from mechanical design
double designP_barg   = 110.0;
double Cp = cost.calcVerticalVesselCost(shellWeight_kg);
double Cbm = cost.calcBareModuleCost(Cp, designP_barg);      // applies Fp & Fm
double Ctm = cost.calcTotalModuleCost(Cbm);                  // + contingency + fees
double Cgr = cost.calcGrassRootsCost(Ctm);                   // + auxiliary facilities

Pattern 2 — End-to-end via `calculateCostEstimate`

cost.calculateCostEstimate(
    Cp,                  // purchased equipment cost
    designP_barg,        // for Fp
    shellWeight_kg,      // for installation man-hours
    "vertical_vessel"    // equipment category
);
String json = cost.toJson();   // structured output for results.json

Pattern 3 — Volume-Based Vessel Cost

For screening work, use the volume-based methods when the mechanical design

knows vessel diameter and length but the shell weight is not yet reliable.

These are now the preferred basis for separator, absorber, column, filter, and

reactor vessel screening.

double vesselVolume_m3 = Math.PI * diameter_m * diameter_m / 4.0 * tanTanLength_m;
double verticalCp = cost.calcVerticalVesselCostByVolume(vesselVolume_m3);
double horizontalCp = cost.calcHorizontalVesselCostByVolume(vesselVolume_m3);

Keep the legacy calcVerticalVesselCost(weight_kg) and

calcHorizontalVesselCost(weight_kg) methods for cases where the mechanical

design has already produced a defensible shell weight.

Pattern 4 — CEPCI Escalation

C_today = C_published × CEPCI_today / CEPCI_published

Built-in indices: CEPCI_2019 (607.5) through CEPCI_2025 (840). Escalate any

literature correlation that's published with a base year.

Pattern 5 — Equipment-Specific Methods

| Equipment | Method | Sizing input |

| ------------------------ | -------------------------------------- | --------------------- |

| Vertical pressure vessel | calcVerticalVesselCost(weight_kg) | shell weight |

| Horizontal vessel | calcHorizontalVesselCost(weight_kg) | shell weight |

| Vertical vessel screening | calcVerticalVesselCostByVolume(volume_m3) | vessel volume |

| Horizontal vessel screening | calcHorizontalVesselCostByVolume(volume_m3) | vessel volume |

| Distillation column | calcColumnShellCost(weight_kg) + calcSieveTraysCost(D, N) | weight + diameter + tray count |

| Shell-tube HX | calcShellTubeHeatExchangerCost(area_m2) | area |

| Plate HX | calcPlateHeatExchangerCost(area_m2) | area |

| Air cooler | calcAirCoolerCost(area_m2) | bare-tube area |

| Centrifugal pump | calcCentrifugalPumpCost(power_kW) | shaft power |

| Centrifugal compressor | calcCentrifugalCompressorCost(power_kW) | shaft power |

| Reciprocating compressor | calcReciprocatingCompressorCost(power_kW) | shaft power |

| Piping | calcPipingCost(D_m, L_m, schedule) | diameter, length |

| Control valve | calcControlValveCost(Cv) | Cv |

Pattern 6 — Mechanical-Design Estimator Wiring

Equipment-specific mechanical designs own their estimator selection. This is

what makes full-process rollups work: ProcessCostEstimate does not need to

know every unit's detailed sizing correlation; it asks the unit for its

mechanical design and cost estimate.

unit.initMechanicalDesign();
MechanicalDesign design = unit.getMechanicalDesign();
design.calcDesign();
design.getCostEstimate().calculateCostEstimate();
double grassRootsCostUSD = design.getCostEstimate().getGrassRootsCost();

Current topside coverage includes specialized mechanical-design/cost paths for

separators, scrubbers, columns, absorbers, adsorbers, mercury removal, pumps,

compressors, expanders, ejectors, heat exchangers, BAHX units, tanks, pipelines,

valves, mixers, splitters, filters, reactors, and manifolds. Header-like units

such as mixers and splitters should calculate dry weight during calcDesign();

filter/reactor/manifold estimators reuse the mechanical design outputs instead

of duplicating sizing logic.

Pattern 7 — Material and Pressure Factors (Turton)

double Fp = CostEstimationCalculator.getPressureFactor(designP_barg);  // ~1.0–3.0
// Fm constants: FM_CARBON_STEEL=1.0, FM_SS304=1.8, FM_SS316=2.1,
//               FM_SS316L=2.3, FM_MONEL=3.2, FM_HASTELLOY_C=3.8, FM_TITANIUM=4.5

Pattern 8 — Stackup Convention

Cp        = purchased equipment, FOB factory          (input)
Cbm       = Cp × (B1 + B2 × Fm × Fp)                  bare module
Ctm       = Cbm × 1.18                                + contingency 15% + fees 3%
Cgr       = Ctm × 1.30                                + 30% auxiliary (utilities, storage, OSBL)

Pattern 9 — Cost Estimate for a Whole Process

ProcessCostEstimate processCost = new ProcessCostEstimate(process);
processCost.calculateAllCosts();
double totalCgr = processCost.getTotalGrassRootsCost();

Use this rollup for reservoir-to-market screening once the flowsheet contains

unit operations for the major equipment. It initializes each unit's mechanical

design, runs calcDesign(), calls the attached estimator, and aggregates the

result by equipment category.

Pattern 10 — Result Schema and Reconciliation

Use CostEstimateResult when handing estimates to reports, agents, or downstream

economics. The map names encode whether rows are additive, summary totals, or

non-cost quantities:

| Map | Meaning | Reconciliation Rule |

| --- | ------- | ------------------- |

| capitalCosts_USD | Additive direct capital-cost lines | Sum only inside the same scope |

| capitalCostBreakdown_USD | Supplementary detail behind a capital line | Do not add to the parent line |

| capitalCostSummary_USD | Capital subtotals/totals | Show as totals; do not re-sum |

| projectCosts_USD | Additive project-cost lines | Sum only inside the matching project scope |

| projectCostSummary_USD | Project subtotals/totals | Show as totals; do not re-sum |

| quantityBasis | Non-cost quantities with units | Never mix into USD totals |

| weightBasis_kg and materialTakeOff | Physical basis and MTO traceability | Keep separate unless building a controlled MTO rollup |

Examples of intended placement:

ProcessCostEstimate.toJson() reports equipment rows with location-adjusted

costs in the standard *_USD fields, because those rows must reconcile with the

process totals and costByEquipmentType_USD. Base, unlocated rows remain under

basePurchasedEquipmentCost_USD, baseBareModuleCost_USD,

baseTotalModuleCost_USD, and baseGrassRootsCost_USD, with locationFactor

shown explicitly.

Common Mistakes

| Mistake | Fix |

| ------------------------------------------------- | ------------------------------------------------------------------- |

| Using outdated CEPCI | Always set setCurrentCepci(CEPCI_<year>) before calculating |

| Hardcoding Fm = 1 | Pick from FM_* constants based on actual material of construction |

| Missing pressure factor at high P | Use getPressureFactor(P) — silently × the cost at HP/HIPPS service |

| Reporting Cp as "installed cost" | Cp is FOB only; installed = at minimum Cbm |

| Mixing currencies | Use setCurrency(code, rate) then read all costs through convertFromUSD/convertToUSD |

| Adding capitalCostSummary_USD into capitalCosts_USD totals | Summary rows are already subtotals/totals; show them separately |

| Treating quantityBasis rows as USD costs | Quantity rows carry units like man-hour or vessel-day, not currency |

| Comparing located process totals to base equipment rows | Use located *_USD equipment fields for reconciliation, base fields for pre-location analysis |

| Claiming Class-3 accuracy on capacity-factored | Capacity factor (six-tenths) → Class 5; named in AACE 18R-97 |

| Ignoring location | setLocationByRegion("Norway") ≈ 1.3× US Gulf Coast for offshore |

| Adding a new mechanical design but leaving the base estimator | Assign the unit-specific costEstimate in the mechanical design constructor |

| Passing shell weight to a volume correlation | Use calc*ByVolume(volume_m3) only with vessel volume |

| SURFCostEstimator for a tie-back or infill template | It adds a default 80 km x 24 in export pipeline (about 340 MUSD) and a 10 km x 14 in infield flowline; call setExportPipelineLengthKm(0.0) and set the infield length/diameter, otherwise the SURF total is 2-3 times too high |

| Expecting PiP, SS-clad or CRA flowline items | SURFCostEstimator prices rigid carbon steel or flexible only; apply an explicit uplift or unit rate (MUSD/km) and state it as an assumption |

| WellCostEstimator well-type strings | Use OIL_PRODUCER, WATER_INJECTOR, GAS_INJECTOR; rig SEMI_SUBMERSIBLE; completion ICD, AICD, OPEN_HOLE, MULTI_ZONE; a default rig day rate applies unless overridden |

Validation Checklist