NeqSim Equipment Cost Estimation Skill
Class-3/4 (AACE 18R-97) order-of-magnitude to study estimates for individual
process equipment and early process/facility CAPEX rollups - the bridge between
sized equipment and a project economics model. Wraps Turton (5e),
Peters–Timmerhaus, Ulrich, and Seider correlations with CEPCI escalation,
material factors, pressure factors, and Lang/Hand factors.
The preferred NeqSim path is mechanical-design driven: call each unit's
initMechanicalDesign(), calcDesign(), then
getMechanicalDesign().getCostEstimate().calculateCostEstimate() or let
ProcessCostEstimate.calculateAllCosts() do that rollup for a full flowsheet.
When to Use
- Quickly cost a sized vessel, column, HX, pump, compressor, filter, reactor, mixer, splitter, or manifold
- Build a bare-module → total-module → grass-roots stackup
- Apply CEPCI to escalate published correlations to current year
- Compare alternatives (e.g. centrifugal vs reciprocating compressor)
- Produce a scope-safe
CostEstimateResultfor equipment, process, topsides, SURF, subsea, well, or field-development estimates - Reconcile located process totals against located equipment rows while retaining base equipment costs
- Feed equipment cost into NPV / IRR via