When this skill is invoked:
- Read the original plan — Find the relevant document:
- If a feature name: read the design doc from
design/docs/ - If a sprint number: read the sprint plan from
production/sprints/ - If a milestone: read the milestone definition from
production/milestones/
- Read the current state — Check what has actually been implemented or is in progress:
- Scan the codebase for files related to the feature/sprint
- Read git log for commits related to this work
- Check for TODO comments that indicate unfinished scope additions
- Compare original vs current scope:
```markdown
## Scope Check: [Feature/Sprint Name]
Generated: [Date]
### Original Scope
[List of items from the original plan]
### Current Scope
[List of items currently implemented or in progress]
### Scope Additions (not in original plan)
| Addition | Who Added | When | Justified? | Effort |
|----------|-----------|------|------------|--------|
| [item] | [commit/person] | [date] | [Yes/No/Unclear] | [S/M/L] |
### Scope Removals (in original but dropped)
| Removed Item | Reason | Impact |
|-------------|--------|--------|
| [item] | [why removed] | [what's affected] |
### Bloat Score
- Original items: [N]
- Current items: [N]
- Items added: [N] (+[X]%)
- Items removed: [N]
- Net scope change: [+/-N] ([X]%)
### Risk Assessment
- Schedule Risk: [Low/Medium/High] — [explanation]
- Quality Risk: [Low/Medium/High] — [explanation]
- Integration Risk: [Low/Medium/High] — [explanation]
### Recommendations
1. Cut: [Items that should be removed to stay on schedule]
2. Defer: [Items that can move to a future sprint/version]
3. Keep: [Additions that are genuinely necessary]
4. Flag: [Items that need a decision from producer/creative-director]
```
- Output the scope check with a clear verdict:
- On Track: Scope within 10% of original
- Minor Creep: 10-25% scope increase — manageable with adjustments
- Significant Creep: 25-50% scope increase — need to cut or extend timeline
- Out of Control: >50% scope increase — stop and re-plan
Rules
- Scope creep is additions without corresponding cuts or timeline extensions
- Not all additions are bad — some are discovered requirements. But they must be acknowledged and accounted for.
- When recommending cuts, prioritize preserving the core user experience over nice-to-haves
- Always quantify scope changes — "it feels bigger" is not actionable, "+35% items" is
Protocol
- Question: Reads feature name, sprint number, or milestone from argument
- Options: Skip
- Decision: Skip — findings are advisory
- Draft: Scope check report shown in conversation only
- Approval: Skip — read-only; no files written
Output
Deliver exactly:
- Scope delta: +X% items vs original plan (quantified, not subjective)
- Additions list: new items not in original plan, each tagged as discovered requirement or gold-plating
- Recommended cuts: specific items to remove to restore original scope (or "None needed")
- Verdict:
ON TRACK/MINOR CREEP/SIGNIFICANT CREEP/OUT OF CONTROL — RE-PLAN