Mfg production planning

From charlieviettq/awesome-agent-skill · View interactive version

Mfg production planning is an AI agent skill from the GitHub repository charlieviettq/awesome-agent-skill. \"Design production plans using MPS (Master Production Schedule), MRP (Material Requirements Planning), and capacity planning. Use this skill when the user needs to schedule production, plan material procurement, balance capacity with demand, or optimize production sequencing — even if they say 'we

How to use this skill

Skill file

Production Planning (MPS/MRP)

Framework

IRON LAW: Plan Hierarchically — Demand → MPS → MRP → Shop Floor

Production planning flows TOP-DOWN:
1. Demand forecast / customer orders → what to make, when
2. MPS → master schedule for finished goods
3. MRP → material and component requirements (what to buy, when)
4. Shop floor scheduling → which machine, which sequence

Skipping levels (going from demand forecast directly to shop floor)
creates chaos — material shortages, capacity conflicts, missed deliveries.

Planning Hierarchy

| Level | Plan | Horizon | Granularity | Decides |

|-------|------|---------|-------------|---------|

| Strategic | S&OP (Sales & Operations Planning) | 12-18 months | Monthly, product family | Capacity investments, workforce planning |

| Tactical | MPS (Master Production Schedule) | 3-6 months | Weekly, end product | What to produce each week |

| Operational | MRP (Material Requirements Planning) | 4-12 weeks | Daily, component/material | What to order, when, how much |

| Execution | Shop Floor Scheduling | 1-2 weeks | Hourly, work center | Sequence, machine assignment |

MPS Process

  1. Inputs: Demand forecast + customer orders + current inventory + safety stock targets
  2. Logic: For each week, calculate: Production Needed = Demand - Beginning Inventory - Scheduled Receipts + Safety Stock
  3. Output: Planned production quantities by week for each finished product
  4. Constraint: Must not exceed available capacity (rough-cut capacity planning check)

MRP Process

  1. Inputs: MPS (what to make) + BOM (Bill of Materials — what it's made of) + Inventory status + Lead times
  2. Logic: "Explode" the BOM — for each finished good, calculate when each component/material must be ordered to arrive in time
  3. Output: Planned purchase orders and production orders with dates and quantities
  4. Key calculation: Order date = Need date - Lead time

Scheduling Algorithms

| Algorithm | Rule | Best When |

|-----------|------|-----------|

| FCFS (First Come First Served) | Process in order received | Low complexity, fairness matters |

| SPT (Shortest Processing Time) | Shortest job first | Minimize average flow time |

| EDD (Earliest Due Date) | Most urgent due date first | Minimize late deliveries |

| Bottleneck-first | Schedule the constraint first, subordinate rest | Capacity-constrained environments (TOC logic) |

SMED (Single-Minute Exchange of Die)

Reduce changeover time to increase flexibility:

  1. Separate internal setup (machine stopped) from external (can do while running)
  2. Convert internal to external where possible
  3. Streamline remaining internal steps
  4. Practice and standardize

Output Format

# Production Plan: {Product/Period}

## Demand vs Capacity
| Week | Demand | Available Capacity | Gap |
|------|--------|-------------------|-----|
| W1 | {units} | {units} | {+/-} |

## Master Production Schedule
| Week | Product A | Product B | Product C | Total |
|------|----------|----------|----------|-------|
| W1 | {units} | {units} | {units} | {units} |

## Material Requirements
| Material | Quantity | Order Date | Supplier | Lead Time |
|----------|---------|-----------|----------|-----------|
| {material} | {qty} | {date} | {supplier} | {days} |

## Scheduling
| Work Center | Mon | Tue | Wed | Thu | Fri |
|------------|-----|-----|-----|-----|-----|
| {center} | {job} | {job} | ... | ... | ... |

Gotchas

References