Mfg oee analysis is an AI agent skill from the GitHub repository charlieviettq/awesome-agent-skill. \"Calculate and diagnose Overall Equipment Effectiveness (OEE) by decomposing into Availability, Performance, and Quality rates. Use this skill when the user needs to measure production line efficiency, identify equipment losses, benchmark manufacturing performance, or justify capital investment — e

How to use this skill

Skill file

OEE Analysis

Framework

IRON LAW: OEE = Availability × Performance × Quality

OEE is a MULTIPLICATIVE metric. 90% × 90% × 90% = 72.9%, not 90%.
Each factor compounds the loss. World-class OEE is 85%+. Most plants
operate at 60-65%. Knowing the TOTAL is useless — you must decompose
to find which factor is dragging performance down.

The Three Factors

| Factor | Formula | Measures | Loss Categories |

|--------|---------|----------|----------------|

| Availability | Run Time / Planned Production Time | Uptime vs downtime | Equipment failures, changeovers, material shortages |

| Performance | (Ideal Cycle Time × Total Count) / Run Time | Actual speed vs design speed | Minor stops, slow running, idling |

| Quality | Good Count / Total Count | Yield, first-pass quality | Defects, rework, scrap, startup rejects |

Six Big Losses (mapped to OEE factors)

| Loss | OEE Factor | Example |

|------|-----------|---------|

| 1. Equipment failure | Availability | Machine breakdown, unplanned repair |

| 2. Setup & changeover | Availability | Product changeover, die change, cleaning |

| 3. Idling & minor stops | Performance | Sensor blockage, jam clearing, small adjustments |

| 4. Reduced speed | Performance | Running below rated speed due to wear or material |

| 5. Process defects | Quality | In-process rejects, rework |

| 6. Startup rejects | Quality | Scrap during warm-up, first-article failures |

Calculation Example

Planned Production Time: 480 min (8-hour shift)
Downtime (breakdowns + changeover): 60 min
Run Time: 420 min

Ideal Cycle Time: 1 min/unit
Total Units Produced: 380

Good Units: 360
Defective Units: 20

Availability = 420 / 480 = 87.5%
Performance = (1 × 380) / 420 = 90.5%
Quality = 360 / 380 = 94.7%

OEE = 87.5% × 90.5% × 94.7% = 75.0%

Diagnosis Steps

Phase 1: Calculate OEE for each production line/machine

Phase 2: Identify the weakest factor (Availability, Performance, or Quality)

Phase 3: Pareto the losses within that factor (which specific loss is biggest?)

Phase 4: Root cause analysis on the top loss (5 Whys, fishbone)

Phase 5: Improve and remeasure

Benchmarks

| OEE Level | Rating | Typical |

|-----------|--------|---------|

| > 85% | World-class | Top manufacturers |

| 60-85% | Typical | Room for improvement |

| 40-60% | Low | Significant losses, urgent action needed |

| < 40% | Critical | Equipment or process fundamentally broken |

Output Format

# OEE Report: {Production Line}

## OEE Summary
| Factor | Value | Benchmark | Status |
|--------|-------|-----------|--------|
| Availability | {%} | >90% | 🟢/🟡/🔴 |
| Performance | {%} | >95% | 🟢/🟡/🔴 |
| Quality | {%} | >99% | 🟢/🟡/🔴 |
| **OEE** | **{%}** | **>85%** | 🟢/🟡/🔴 |

## Loss Breakdown
| Loss | Minutes Lost | % of Total Loss | Priority |
|------|-------------|----------------|---------|
| {loss type} | {min} | {%} | 1/2/3 |

## Root Cause (Top Loss)
{5 Whys or fishbone analysis}

## Improvement Plan
| Action | Target Impact | Timeline | Owner |
|--------|-------------|----------|-------|
| {action} | +{X%} OEE | {weeks} | {who} |

Gotchas

References