Sprint status

From striderZA/OpenCodeGameStudios · View interactive version

Sprint status is an AI agent skill from the GitHub repository striderZA/OpenCodeGameStudios. Fast sprint status check. Reads the current sprint plan, scans story files for status, and produces a concise progress snapshot with burndown assessment and emerging risks. Run at any time during a sprint for quick situational awareness. Use when user asks 'how is the sprint going', 'sprint update',

How to use this skill

Skill file

Sprint Status

This is a fast situational awareness check, not a sprint review. It reads the

current sprint plan and story files, scans for status markers, and produces a

concise snapshot in under 30 lines. For detailed sprint management, use

/sprint-plan update or /milestone-review.

This skill is read-only. It never proposes changes, never asks to write

files, and makes at most one concrete recommendation.


1. Find the Sprint

Argument: $ARGUMENTS[0] (blank = use current sprint)

production/sprints/ for a file matching sprint-03.md, sprint-3.md,

or similar. Report which file was found.

production/sprints/ and treat it as the current sprint.

files found. Start a sprint with /sprint-plan new." Then stop.

Read the sprint file in full. Extract:

Nice to Have), owner, and estimate


2. Calculate Days Remaining

Using today's date and the sprint end date from the sprint file, calculate:

If the sprint file does not include explicit dates, note "Sprint dates not

found — burndown assessment skipped."


3. Scan Story Status

First: check for production/sprint-status.yaml.

If it exists, read it directly — it is the authoritative source of truth.

Extract status for each story from the status field. No markdown scanning needed.

Use its sprint, goal, start, end fields instead of re-parsing the sprint plan.

If sprint-status.yaml does not exist (legacy sprint or first-time setup),

fall back to markdown scanning:

  1. If the entry references a story file path, check if the file exists.

Read the file and scan for status markers: DONE, COMPLETE, IN PROGRESS,

BLOCKED, NOT STARTED (case-insensitive).

  1. If the entry has no file path (inline task in the sprint plan), scan the

sprint plan itself for status markers next to that entry.

  1. If no status marker is found, classify as NOT STARTED.
  2. If a file is referenced but does not exist, classify as MISSING and note it.

When using the fallback, add a note at the bottom of the output:

"⚠ No sprint-status.yaml found — status inferred from markdown. Run /sprint-plan update to generate one."

Optionally (fast check only — do not do a deep scan): grep src/ for a

directory or file name that matches the story's system slug to check for

implementation evidence. This is a hint only, not a definitive status.

Stale Story Detection

After collecting status for all stories, check each IN PROGRESS story for staleness:

Last Updated: field in the frontmatter or header (e.g., Last Updated: 2026-04-01

or updated: 2026-04-01). Accept any reasonable date field name: Last Updated,

Updated, last-updated, updated_at.

STALE stories are included in the output table and collected into an "Attention Needed"

section (see Phase 5 output format).

Stale story escalation: If any IN PROGRESS story is flagged STALE, the burndown verdict

is upgraded to at least At Risk — even if the completion percentage is within the normal

On Track window. Record this escalation reason: "At Risk — [N] story(ies) with no progress in

[N] days."


4. Burndown Assessment

Calculate:

Assess burndown by comparing completion percentage to time consumed percentage:

If dates are unavailable, skip the burndown assessment and report "On Track /

At Risk / Behind: unknown — sprint dates not found."


5. Output

Keep the total output to 30 lines or fewer. Use this format:

## Sprint [N] Status — [Today's Date]
**Sprint Goal**: [from sprint plan]
**Days Remaining**: [N] of [total] ([% time consumed])

### Progress: [complete/total] tasks ([%])

| Story / Task         | Priority   | Status      | Owner   | Blocker        |
|----------------------|------------|-------------|---------|----------------|
| [title]              | Must Have  | DONE        | [owner] |                |
| [title]              | Must Have  | IN PROGRESS | [owner] |                |
| [title]              | Must Have  | BLOCKED     | [owner] | [brief reason] |
| [title]              | Should Have| NOT STARTED | [owner] |                |

### Attention Needed
| Story / Task         | Status      | Last Updated   | Days Stale | Note           |
|----------------------|-------------|----------------|------------|----------------|
| [title]              | IN PROGRESS | [date or N/A]  | [N days]   | [STALE / no timestamp — cannot check staleness / inline task — cannot check staleness] |

*(Omit this section entirely if no IN PROGRESS stories are stale or have timestamp concerns.)*

### Burndown: [On Track / At Risk / Behind]
[1-2 sentences. If behind: which Must Haves are at risk. If on track: confirm
and note any Should Haves the team could pull.]

### Must-Haves at Risk
[List any Must Have stories that are BLOCKED or NOT STARTED with less than
40% of sprint time remaining. If none, write "None."]

### Emerging Risks
[Any risks visible from the story scan: missing files, cascading blockers,
stories with no owner. If none, write "None identified."]

### Recommendation
[One concrete action, or "Sprint is on track — no action needed."]

6. Fast Escalation Rules

Apply these rules before outputting, and place the flag at the TOP of the

output if triggered (above the status table):

Critical flag — if Must Have stories are BLOCKED or NOT STARTED and

less than 40% of the sprint time remains:

SPRINT AT RISK: [N] Must Have stories are not complete with [X]% of sprint
time remaining. Recommend replanning with `/sprint-plan update`.

Completion flag — if all Must Have stories are DONE:

All Must Haves complete. Team can pull from Should Have backlog.

Missing stories flag — if any referenced story files do not exist:

NOTE: [N] story files referenced in the sprint plan are missing.
Run `/story-readiness sprint` to validate story file coverage.

Collaborative Protocol

This skill is read-only. It reports observed facts from files on disk.

For more detail on a specific story, the user can read the story file directly

or run /story-readiness [path].

For sprint replanning, use /sprint-plan update.

For end-of-sprint retrospective, use /milestone-review.